Open the histograms
On the 5. Activities Relationships_Durations step, click the Histograms tab.
Set a maximum
Click the Max (head/day) cell of a resource, for example Carpenter, and type the limit you want, such as 4.
See the limit line
A line is drawn on the chart at the limit you entered.
Early and late dates
Use Early and Late to switch the chart between early dates and late dates.
Show the cost
Click the Cost row in the resource list to see the cost per month.
Show it as a line
Click Lines to draw the monthly cost as a line instead of bars.
How to View Resource Histograms and the Cost per Month?
Show monthly resource hours, set a maximum limit line and show the cost curve
Guide 32 of 36 in Baseline creating