Click the first cell
In the row of the item, click the cell under the first WBS element, for example 1 - Substructure works.
Type the first percentage
Type 10 and press Enter.
Click the second cell
Click the cell of the same row under the second WBS element, for example 2 - Super Structure, and type 90.
Check the total
The two percentages must add up to 100%. Group Total shows 100.0% in green when they do.
How to Split a BOQ Item Between Two WBS Elements?
Give part of an item to one WBS element and the rest to another
Guide 27 of 36 in Baseline creating