Start with the first WBS level
With L1 selected there is one WBS column. Click the all % box in the column header.
Type 100
Type 100 and press Enter. Every row gets 100% and Row Total turns green. The ALLOCATION counter shows how many items are fully assigned.
Go to the next WBS level
Click L2 to see the WBS elements of the second level as columns.
Click a cell
Click the cell where the BOQ item (row) meets the WBS element (column) that it belongs to.
Type the percentage
Type the percentage, for example 100, and press Enter. The item is now assigned to that WBS element.
Check the total
The total of each row must be 100%. The Group Total column turns green at 100.0% and stays red if the row is not complete.
Note: Repeat for every row, then click Save. Do the same on L3.
How to Assign BOQ Items to WBS Elements by Percentage?
Give each BOQ item or activity 100% across your WBS elements
Guide 23 of 36 in Baseline creating