Open the schedule step
Go to 5. Activities Relationships_Durations. The schedule is empty until the CPM is run.
Run the CPM calculation
Under CPM, click Run CPM Calculation.
Generate the relationships
Under RELATIONSHIPS, click the first button to generate the relationships. The dates and Gantt chart update.
Sort by start or finish
Click the Early Start or Early Finish column header to sort the schedule by start or finish date.
How to Generate Relationships and Run the CPM?
Create the schedule logic, calculate the dates and sort by start date
Guide 29 of 36 in Baseline creating