Save the BOQ step
When you are happy with the BOQ Cleaning step, click Save.
Go to the next step
Click the Next Step button to move to 2. WBS Creation.
Add a level
The WBS Builder has the Levels Library on the left and the Project WBS on the right. Click the (+) button in the Levels Library to add a level.
Name the level and give it an abbreviation
Type the abbreviation in the small box on the left (for example TY) and the level name in the wide box (for example Type of works).
Note: The abbreviation is used in the IDs of the WBS elements, and it is also used in the activity ID.
How to Create WBS Levels in the WBS Builder?
Save step 1, open the WBS Builder and add a level with an abbreviation
Guide 20 of 36 in Baseline creating