What Is Included in the Weekly Report [Report Template]
A planning engineer’s job does not end with the approval of the baseline schedule. In fact, this is where the challenge begins. As the project progresses, regular updates, follow-ups, and expected changes require careful monitoring to ensure alignment with the project objectives. One of the key responsibilities during this phase is the preparation and submission of the weekly report, an important document that provides stakeholders with an overview of project performance.
However, the weekly report alone may not be sufficient to convey the full picture. Supporting documents can add clarity, provide deeper insights, and justify reported progress, delays, or critical changes. In this article, we will explore the essential documents that can be submitted alongside the weekly report.
Content That is Preferred to be in The Weekly Report
A weekly report submitted to the consultant for tracking project progress should provide a clear and brief overview of the project’s status, highlighting key performance indicators, challenges, and necessary actions. Here’s what it should include:
Ready to take your skills to the next level? 🚀 Check out our Special Online Courses! 🚀
Gain valuable insights, boost your career, and learn from industry experts.
1. Safety Measurement for this period
This section typically includes key metrics such as the number of safe manhours worked, incidents or near misses reported, safety audits conducted, and corrective actions taken. By documenting safety performance regularly, the project team ensures compliance with regulations.
2. Executive Summary
What is the Name of the project, the total project cost, and the number of units (Zones, phases, etc.) in the project. And most importantly, the data date of the report. The consultant may be tracking several projects, so providing a summary is necessary to avoid confusion and misunderstandings.
Example:
The Weekly report should provide some of the important data that are in Primavera P6 such as the status of procurement, Engineering and Construction WBS’s, and of course the Schedule Percentage Complete and Performance Percentage Complete, so that it is easy and clean for the reader or whoever the person that will be reading the report if the project is on track or delayed.
Example:
3. Progress Update
In this section, we explain in detail the progress made in each WBS. For example, in the Engineering WBS, we explain how many shop drawings were submitted, how many are under review, and whether we are working according to schedule or ahead. Most importantly, the delays in each WBS.
This goes on on all the WBSs in the schedule to provide accurate information.

Data Management and Reporting
Data Management is the key success of construction projects reporting. This self-study course will teach you using a step by step case…
- 1,674 students
- WhatsApp support group
- Certificate
4. Major Works Done During this Period
This section should detail the key activities completed, highlight any major milestones. It serves as a factual record of what has been done compared to the planned activities, helping all stakeholders understand whether the project is advancing as expected.
Example:
Documents That Can Be Attached to the Weekly Progress Report
Here are some additional sections that can be added to enhance the Weekly Report:
1. Look-Ahead Schedule (Next Week)
This can help in acknowledging what should be done in the next week and the resources needed to plan ahead, so that you do not miss or fail to provide the resources. This can be achieved with Primavera P6. You can read our article about Primavera P6 filters here. Or you can create a Lookahead on Excel, and here is how in this link.
Example:
2. Risks and issues
If there are risks or delays that concern the consultant or the owner, the contractor can submit a recommendation or action plan to overcome the risks, prevent the delay from occurring, or decrease the delay duration by the actions provided. You can find more information about the risk register in our article here.
Example:
3. Invoices
The Payment section of the weekly report focuses on the financial aspect of the project, specifically the value of work completed during the reporting period. It should include the amount of work that is eligible for invoicing, typically linked to the approved Bill of Quantities (BOQ) or payment schedule. This section helps in monitoring the project’s cash flow and ensuring that financial progress aligns with the physical progress on site.
4. Photos from the Site
This section can help in providing actual evidence to be used in the future in any discussion or meeting, if the contractor submitted alongside the weekly report photos saying that he could not access the site because the owner did not provide a site clear form any obstacles, this can help the contractor in the future in any claim.
Note
You can enroll in our Data Management and Reporting Course to learn more about how to use the data and create informative reports. You can also learn how to create reports by using Power Bi software from our Power Bi Monitoring and Controlling with P6 course.
If you are one of our students, you can find a free report template in the Data Management and Reporting course.
Conclusion
Weekly progress reports play a role in maintaining transparency, ensuring alignment between all stakeholders, and keeping the project on track. They serve as a structured tool to communicate actual progress, highlight potential risks, and support decision-making. However, a report alone may not always provide the full picture. Attaching supporting documents such as site photos and look-ahead schedules adds clarity, provides deeper insights, and helps justify reported progress, delays, or critical changes. By incorporating these attachments, planning engineers can emphasize the accuracy of their reports, smooth informed discussions, and ensure that all project updates are well-documented and backed by verifiable data.
Download the Resources of this Article
What Is Included in the Weekly Report [Report Template] 3.22 MB 1125 downloads
Keep growing with Planning Engineer
Learn with a clear path
From Primavera P6 basics to claims, cost control and Power BI. Start with our free courses.
Browse coursesGet help on WhatsApp
Every course comes with a private WhatsApp support group where our team answers your questions.
Join a courseFind planning jobs
25 open planning and project control jobs. Post your resume so employers can find you.
See jobsGet tips by email
Free planning tips, templates and course offers. Unsubscribe any time.









![S-Curve from Primavera P6 [Template]](https://planningengineer.net/wp-content/uploads/2025/03/S-Curve-from-Primavera-P6-Template-600x400.png)