Week 1 Primavera Sample Project for Discussion -Construction Works At Camp
Project description: the project scope is consists of 4 facilities, facility no. 0 which is site works and external works (telephone, street lighting and connecting L.V cables to feed the building and other facilities), facility no. 1 which is dinning hall, facility no. 3 which is Artificial Grass football playground and facility no. 4 which is multipurpose sports field (rubber flooring playground) and finally test and commissioning of all the project.
This is an open discussion about the attached primavera schedule, This schedule submitted from our site member and we need to help improving the quality of the time schedules as we discuss the mistakes and the ways to make such schedule looks better.
Download the schedule from the following link:
Download primavera files
[download#5]
I will add one comment and leave other comments for you
My comment: There are no procurement and delivery section for materials, This is very important section and should be well defined.
Now your turn, what are your comments ?
If you want to share your sample project schedule for discussion, send it to me as per the following:
1- Project Name and good description to allow us to understand your project to comment on it.
2- Project XER File
3- Project PDF File
4- Send it to [email protected]
Leave A Reply
You must be logged in to post a comment.
28 Comments
Hi. The rar file is corrupted. is it the xer file?
There is no local authority related item to obtain electricity, telephone, civil defence, and municipality approval which is an important item in the project
The file is corrupted…
The rar file 12058.rar is is corrupted, unable to open it
12058.rar is broken!
First we need the xer file of the project, which we couldnโt download, it says its corrupt!
Then we can put a plan to estimate how good is the schedule, we should focus on how it was built, organized, linked and how it was scheduled, then a look at resource and cost management.
To achieve that we should have a look (if possible) at projectโs documentation, then dates, duration and deadlines, WBS structure, Activities types, project calendars, measure Milestones, Find open ended relationships, find leads and lags, check constraints and out of sequence activities. Critical Path and total float, resource assignments, find resource over-allocation, check cost loading, and earned value.
The file is corrupted
Yeh kis ka banaya hai bhai
Thank you for your mail, I did download both files , the pdf one opens and is OK, the other 12058.rar, I'm not able to open it as its giving that its damaged, so would you please check it once again, only the pdf file is not enough to comment on the schedule, Thanks.
the file 12058.rar is corrupted
Call for Admin….. many people would like to add to this great exercise… but admin of this websites seems to be busy as we didn't see any response to many of the fellows comments that the XER file is corrupted. Fankely speeking good comments could not be made on the schedule viability as long as XER file is not available. We need Admin to jump in and reattach the XER file as it si corrupted.
Further to the above my suggestion for the comments are;
1) In order to make sequential comments or step by step comments we should choose one topic and stick to that for commenting. as long as that topic is exhausted and fully understand the problems in the schedule related to that perticular topics we will move to another area of schedule validation.
my Openion for sequential comments are
1) The Schedule Capture all activities or not (like the Admin commented that the Schedule is lacking with procurement activities, WBS should be product oriented, Represent activities of the Engineer and Client etc.)
2) sequencing Activities (e.g Network should be complete, mazimise use of FS logic and minimize/no use of SF logic, Constraint, Lags/Leads, etc)
3) resource Allocation
4) Valid Duration
5) Validitiy of Critical Path
6) Reasonable Total Float etc.
Check now, the files should be working
Check now, the files should be working
Check now, the files should be working
Check now, the files should be working
Check now, the files should be working
Check now, the files should be working
Check now, the files should be working
Planning Engineer ……… Sir, still there is a problem with the file when i have tried to import it into excell… the file is invalid…….. i dont know whats the issue…….. is there any version problem… i am using P6V7..
please suggest
Sorry not excell, but Primavera P6
Dear Planning Engineer…… Week 1 is near to finish and we are just could not escape the problem of XER file…. ๐ we are getting very slow response form your side… please help improve the system
Dear all, sorry for late to reply, I sent the file again to the admin, hope it will work, I will be happy to see your comments
Comment came by Email
1/ It is true โ between concrete slab and plasters there is enough time โ around 3 weeks, but to me the activities as concrete curing, mounting/dismantlement of scaffolding and shuttering should present โ they could become critical!
In addition with this level of detailization of the resources, missed activities resources as curing compound, sets of scaffolding or shuttering etc. will remind hidden and easily missed!
2/ The same for production and supply activities โ they are missing, if kitchen cabinets subcontractor delays the production or supply, how planner will prove who is responsible for the delay of mounting of kitchen cabinets?
ูุงุฃุฎู ุงูุชูุฑูู ูุนุจุฑูู ูู ู ุงููุด ุนูุด ูุจุฑูุณุช ููุง ุงูู
ูุงุฃุฎู ุงูุชูุฑูู ูุนุจุฑูู ูู ู ุงููุด ุนูุด ูุจุฑูุณุช ููุง ุงูู
Mahmoud Saleh ูููููููููููู … ุฃููุข ุจุฃุฎู ุงูุนุฒูุฒ ู ููุฏุณ ู ุญู ูุฏ … ุฃุฎุจุงุฑู ุฅูู ..ูุฃุณุฑุชู ุงููุฑูู ู ูุนููู ุจุฎูุฑ
ุฅุจูู ุฅุชุตู ูุง ุฑูุณ ุนูุดุงู ูุนุฑู ุฃุฎุจุงุฑู ููุทู ู ุนููู … (ุชูููููู 00201003070328 ) ..
ูู ุณูู ูุงูุช ุทูุจ ูุงุญุจูุจ ููุจู ูุจุนุฏุฉ ุงูุฃูุงู ููุฌุนููุง ุฑุจูุง ุนูุฏ ุณุนูุฏ ุนูููุง ูุนูููู
hi im new to planning department and im very much nee in learning P6
can i get sample any residential project for practising in p6 and how to input all activities i.e procedure for inputting task and get the results.