Week 2 Primavera Discussion -constructing a house of three floor
Project description:This is for constructing a house of three floor and roof and its final finishes with the engineering work and shopdrawing
This is an open discussion about the attached primavera schedule, This schedule submitted from our site member and we need to help improving the quality of the time schedules as we discuss the mistakes and the ways to make such schedule looks better.
Ready to take your skills to the next level? 🚀 Check out our Special Online Courses! 🚀
Gain valuable insights, boost your career, and learn from industry experts.
Download the schedule from the following link:

Primavera Online Basic Course -English
Online Primavera P6 Course for Engineers & Construction Managers Learn how to use Oracle Primavera P6 to plan, schedule, monitor, and control…
- 5,312 students
- WhatsApp support group
- Certificate
If you want to share your sample project schedule for discussion, send it to me as per the following:
1- Project Name and good description to allow us to understand your project to comment on it.
2- Project XER File
3- Project PDF File
4- Send it to [email protected]
Keep growing with Planning Engineer
Learn with a clear path
From Primavera P6 basics to claims, cost control and Power BI. Start with our free courses.
Browse coursesGet help on WhatsApp
Every course comes with a private WhatsApp support group where our team answers your questions.
Join a courseFind planning jobs
25 open planning and project control jobs. Post your resume so employers can find you.
See jobsGet tips by email
Free planning tips, templates and course offers. Unsubscribe any time.
Leave A Reply
You must be logged in to post a comment.









7 Comments
how the masonary works starts immediately after the finish of the slabs concrete pouring
u r right assuming basement masonary start after casting ground slab
or but lag when connect it to basement slab
hi, there is a problem here, I downloaded the wk2.rar file but I'm not able to open it, also last week xer file, I couldn't import to Primavera P6, I'm using version 8.3 which should open all previous versions but still not able to import, please check this mater and find a solution, as last week there were who had the same problems like me and still not solve yet.
Thnx.
It might be possible that this schedule could be made in P6 older versions. Therefore open this with notepad and change the version to 8.3 then save this file and try to import it again. I hope it will be opened.
Activities with Actual Dates > Data Date…………………….1
Project: TP Activity: 340 1ST FLOOR MASONARY WORK
Out-of-sequence activities…………………………………1
Project: TP Activity: 340 1ST FLOOR MASONARY WORK
Activities must have successors………………………………5
Project: TP Activity: 1570 ISOLATION MATERIAL SUBMITAL
Project: TP Activity: 1690 RED TILES MATERIAL SUBMITAL
check the predecessors…………………………….
Project: TP Activity: 1410 R.C SHOPDRAWING SUBMITAL
good
great