Method statements are very important documents for all engineers to know how to plan and execute different activities. Whether you are a planning engineer, site engineer, construction manager, or project manager, you defiantly need to have method statement library. My …
1. SCOPE This procedure covers controls to be carried out during construction of underground sewerage and surface water drainage works.
Preparation of Work, Materials and Components: i) When the materials and components are distributed to the work area, ensure that the structure is not overloaded. ii) Plan for scaffolding material required for work at heights. Plan for additional manpower for …
1. SCOPE This procedure applies to the installation of formwork and the controls required during assembly, erection and final positioning of formwork used in Structural concrete operations. 2. PROCEDURE .1 All formwork activities will be carried out in accordance with the specification.
A Block Work Method Statement is a document commonly used in construction projects, especially in the building and masonry sector. It outlines the procedures, sequence of activities, safety measures, and other relevant details necessary for carrying out block work or …
CONSTRUCTION JOINTS IN IN-SITU CONCRETE METHOD STATEMENT 1. SCOPE The scope of this procedure outlines methods to be used for constructing effective and durable construction joints in accordance with the contract specifications. 2. PROCEDURE .1 In some cases CLIENT shall have to prepare …
The scope of this procedure covers the control of installation of in-situ concrete paving surfaces including finishes to ensure compliance with the contract specifications.
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement
This procedure outlines the system of control and inspections to be adopted for the fixing on site of tiles and mosaics.
Batching Of Concrete Method Statement
The scope of this procedure covers checks required to be carried out prior to and during the site batching of concrete.
The scope of this procedure covers the control of installation of Bored Cast-in-Situ Concrete piles executed by a sub-contractor.