Method Statement installation of PVC Conduits Concealed in Concrete Slab and Concrete Walls
Introduction:
This method statement covers the site installation of the PVC Conduits in the floor slab & concrete walls.
This procedure defines the method used to ensure that all conduits and associated accessories: bends, tees, couplers, reducers, and all accessories associated with the systems installed are correct and acceptable. Similarity to other activities.

Ready to take your skills to the next level? 🚀 Check out our Special Online Courses! 🚀
Gain valuable insights, boost your career, and learn from industry experts.
PVC Conduits:
The installation of PVC Conduits within Concrete Slabs and Concrete Walls is a crucial component of the Power & Lighting Wiring system. This section will guide you through the necessary steps to ensure a successful installation.

Installation Steps:
Review Approved Shop Drawing:
Begin by reviewing the approved shop drawing, which includes essential details about the Conduit’s layout, diameter, and the location of conduits in Slabs and Walls.
Prepare conduits.
Ensure that approved material required to conduct work will be available.
Before the beginning of work, the area and access will be inspected to confirm that the site is ready to commence the work.
The site engineer/supervisor will also check that the tools and equipment available comply with contract requirements.
Mark PVC Conduits Locations
The supervisor will ensure that all the grid lines and datum lines are marked by the surveyor and that all the routes and marking are based on the datum line provided by the surveyor.
The supervisor will conduct a site survey and mark the route of conduits as per approved drawings. If there are any difficulties in executing the work, these will be brought to the notice of the engineer for corrective action.

Data Management and Reporting
Data Management is the key success of construction projects reporting. This self-study course will teach you using a step by step case…
- 1,690 students
- WhatsApp support group
- Certificate
Conduit Size
PVC conduits of the correct sizes will be used for concealment of electrical services in the concrete walls & slabs.
The minimum conduit size used will be 20 mm in diameter. The conduit size selection is made as per technical specifications and approved shop drawings.
How to install conduits
Bending the PVC conduits
Wherever conduit is to be installed in vertical walls the run of conduit will be kept straight.
The bending of conduits will be done using proper bending springs and the straight lengths of conduits are coupled using standard couplers glued using good quality PVC sealant.
Fixing the PVC conduits
All the cast-in conduits will be firmly bent to the steel rebar and conduits are placed sandwiched between rebars so that future drilling of anchors should not damage cast-in conduits and the installed wires.
Wherever cast-in conduits are to be terminated onto back boxes standard conduit accessories approved in the material submittal will be used.
The relationship between PVC conduit installation and other activities:
Predecessor | Activity name | Successor |
Reinforcement for Slabs and concrete walls | PVC Conduits | Concrete for slabs and concrete walls |
Productivity rate for PVC conduits installation:
Productivity rate:
Linear meter/day = 80
Hour/Linear meter = 0.10
Labor Requirement Per Group:
1 Electrician
1 Helper/unskilled Labor
Download the Resources of this Article
Method Statement installation of PVC Conduits in Slab and Walls 347.62 KB 4507 downloads
Keep growing with Planning Engineer
Learn with a clear path
From Primavera P6 basics to claims, cost control and Power BI. Start with our free courses.
Browse coursesGet help on WhatsApp
Every course comes with a private WhatsApp support group where our team answers your questions.
Join a courseFind planning jobs
68 open planning and project control jobs. Post your resume so employers can find you.
See jobsGet tips by email
Free planning tips, templates and course offers. Unsubscribe any time.
Tag:concealed condiuts, method statement, Method Statement installation of PVC Conduits Concealed in Concrete Slab, Method Statement installation of PVC Conduits Concealed in Concrete Slab and Concrete Walls, Method Statement installation of PVC Conduits Concealed in Concrete Walls, PVC Conduits, pvc Conduits method statement








![S-Curve from Primavera P6 [Template]](https://planningengineer.net/wp-content/uploads/2025/03/S-Curve-from-Primavera-P6-Template-600x400.png)