Underground Sewerage and Surface Water Drainage Method Statement
1. SCOPE
This procedure covers controls to be carried out during the construction of underground sewerage and surface water drainage works.
2. PROCEDURE
1. All underground sewerage and surface water drainage works will be done according to the contract specification and good practice. Where specifications are not provided or are incomplete, the matter shall be referred back to the consultant for additional information.
2. Depending upon the complexity of the work and the requirements of the PQP, a method statement shall be prepared and approved by the consultant which shall include the following:
Ready to take your skills to the next level? 🚀 Check out our Special Online Courses! 🚀
Gain valuable insights, boost your career, and learn from industry experts.
· Proposed plant and equipment.
· Jointing technique.
· Trench support (in case of deep excavation).
· Manufacturer’s jointing and installation details and test certificates (where relevant).
· The sequence of activities.
· Compaction method and quality of fill material.
· Test plan.

Data Management and Reporting
Data Management is the key success of construction projects reporting. This self-study course will teach you using a step by step case…
- 1,674 students
- WhatsApp support group
- Certificate
3. Check delivery orders and certificates against the specifications and examine marks, labels, and conditions of material and components.
4. Unload and handle materials and components with care to minimize damage and soiling.
5. Before commencing excavation, fence or board the area of work to prevent unauthorized access. Provide adequate safeguards, e.g. gangways, handrails, notices or direction boards, and lighting at night.
6. Contact local authority departments to obtain details of existing underground services. Proper marking will be employed on the site to avoid damage to any adjacent services.
7. Provide adequate trench support to retain the sides of excavations and ensure the safe and proper construction of works and completion of backfilling.
8. Spoil heaps of stacked material and vehicles to be kept at a distance of more than the trench depth from the trench.
9. Temporary supports to excavations will be maintained in position until sufficient backfill has been placed and compacted to ensure the stability of the sides of the excavation.
10. Employ the proper jointing method as recommended by the pipe manufacturer. Ensure that jointing faces are dry, clean, and free from soil or bedding particles.
11. Finalize an intermediate test plan and water testing to check the pipeline’s water tightness.
3. DOCUMENTATION
1. Appendix FOUN/06A and Appendix FOUN/06/B shall be used to monitor drainage construction. Approval to proceed will be given by the QA/QC.

installation of underground sewerage and surface water drainage works
Don’t forget to download the Attachment: CONTROL OF SEWERAGE AND SURFACE WATER DRAINAGE
You may be interested in “ Method Statement of Drainage Pipe Installation “
Download the Resources of this Article
Underground Sewerage and Surface Water Drainage Method Statement 280.85 KB 8804 downloads
Keep growing with Planning Engineer
Learn with a clear path
From Primavera P6 basics to claims, cost control and Power BI. Start with our free courses.
Browse coursesGet help on WhatsApp
Every course comes with a private WhatsApp support group where our team answers your questions.
Join a courseFind planning jobs
25 open planning and project control jobs. Post your resume so employers can find you.
See jobsGet tips by email
Free planning tips, templates and course offers. Unsubscribe any time.








![S-Curve from Primavera P6 [Template]](https://planningengineer.net/wp-content/uploads/2025/03/S-Curve-from-Primavera-P6-Template-600x400.png)