MEP Commissioning Check Lists
At the end of every construction project there are list of check-up for the equipment and systems involves in the project. This procedure called Commissioning, and it is required to obtain the client final approval on the project and issue the final completion certificate. In this post you will find the most common systems for MEP Commissioning along with the associated forms and actions to be done. Each system will be available for download in separate page within this post.
Page 1 chilled water pump
Page 2 air handling unit
Page 3 fan coil unit
Page 4 extract fans
Page 5 cold water transfer pump sets
Page 6 sump pump
Page 7 sprinkler + wet booster set
Page 8 air distribution system
Page 9 chilled water distribution system
Page 10 earthing and earth bonding
Page 11 music and public address system
Page 12 MATV system
Page 13 CCTV surveillance
Page 14 fire alarm system
Page 15 power and control cables
Page 16 motor control centre
Page 17 main distribution boards and sub main distribution boards
Page 18 final circuits and distribution boards
-
COMMISSIONING CHECK SHEET FOR CHILLED WATER PUMP
PROJECT: PROJECT NAME SITE NO.: | ||||||
COMMISSIONING CHECK SHEET FOR CHILLED WATER PUMP
|
Sheet No. | |||||
SUBCONTRACTOR:
EQUIPMENT NO. : SEQUENCE NO. : SERIAL NO. : DATE : LOCATION : COMMISSIONED ON :
|
||||||
ITEM |
POINTS TO BE CHECKED |
Checked by |
REMARKS |
|||
1 |
Chilled water distribution network pressure tested and cleared. | |||||
2 |
Makeup connection made. | |||||
3 |
Dosing pot connected. | |||||
4 |
Strainers are cleaned. | |||||
5 |
Drain connections to all equipment provided. | |||||
6 |
Pressure gauges and flow switches are installed. | |||||
7 |
Tightness of electrical connections. | |||||
8 |
Supply voltage and motor rating. | |||||
9 |
Free rotation of impeller. | |||||
10 |
MCC is clean. | |||||
11 |
Pump and motor are clean. | |||||
12 |
Overload setting and fuse rating. | |||||
13 |
Pump and motor alignment. | |||||
14 |
Pumps are interfaced with BMS. | |||||
15 |
Pumps are in manual made. | |||||
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT SPECIFICATIONS. | ||||||
CHECKED BY SUBCONTRACTOR: _____________________Signature | ||||||
WITNESSED BY CLIENT: ______________________Signature | ||||||
WITNESSED / ACCEPTED BY CONSULTANT: ____________________Signature |
Download the commissioning check sheet for chilled water pump in word format:COMMISSIONING CHECK SHEET FOR CHILLED WATER PUMP
Go to Next Page for the next commissioning check sheet
Tag:air distribution system, air handling unit, CCTV surveillance, check sheet, checked checked, chilled water distribution system, chilled water pump, cold water transfer pump, commissioning check, earthing and earth bonding, extract fans, fan coil unit, final circuits and distribution boards, fire alarm system, MATV system, MEP Commissioning, motor control centre, nbsp nbsp, power and control cables, project project, public address system, signature nbsp, signature witnessed, sprinkler, sump pump, wet booster