PDM Method Excel Sheet
Nice share from our website member Engineer Mudassir Jamal about PDM Method. Mainly we have Forward Pass Calculate Early Dates hence the Free Float & Total Duration of the Project As longest Path, and Backword Pass Calculates the Late Dates hence the Total Floats & Critical Path of the Project.
FF (Free Float) = Simple formula to calculate Free Float is ES (of successor) – EF of current activity
Ready to take your skills to the next level? 🚀 Check out our Special Online Courses! 🚀
Gain valuable insights, boost your career, and learn from industry experts.
TF (Total Float) = Simple formula to calculate total float is our usual formula i.e. LS (Late Start) – ES (Early Start) or LF (Late, Finish) – EF (Early Finish)
Download the excel sheet: PDM METHOD
Keep growing with Planning Engineer
Learn with a clear path
From Primavera P6 basics to claims, cost control and Power BI. Start with our free courses.
Browse coursesGet help on WhatsApp
Every course comes with a private WhatsApp support group where our team answers your questions.
Join a courseFind planning jobs
25 open planning and project control jobs. Post your resume so employers can find you.
See jobsGet tips by email
Free planning tips, templates and course offers. Unsubscribe any time.
Tag:free float, PDM Method, total float
Leave A Reply
You must be logged in to post a comment.








![What Is Included in the Weekly Report [Report Template]](https://planningengineer.net/wp-content/uploads/2025/05/What-Is-Included-in-the-Weekly-Report-Report-Template-600x400.png)

1 Comment
Thanks , nicely explained.