WBS Dictionary Template
WBS Dictionary Template, and description of each field how to be filled.
Project Title: |
Date Prepared: |
Work Package Name: From the WBS | WBS ID: From the WBS | ||||||||
Description of Work: Description of the work to be delivered in sufficient detail to ensure a common understanding by stakeholders. |
|||||||||
Milestones: 1. List any milestones associated with the work package. 2. 3. |
Due Dates: List the due dates of the milestones. |
||||||||
ID |
Activity |
Resource |
Labor |
Material |
Total Cost |
||||
Hours |
Rate |
Total |
Units |
Cost |
Total |
||||
From Activity list or schedule |
From Resource requirements |
Total effort. |
Labor rate. |
Hours X rate. |
Amount |
Cost |
Units X cost. |
Labor + Material. |
|
Quality Requirements: Quality metrics used to verify the deliverable. |
|||||||||
Acceptance Criteria: Criteria that will be used to accept the WBS element. |
|||||||||
Technical Information: Technical information or reference to technical documentation that contains technical information. |
|||||||||
Contract Information: Relevant contract information that contains constraints, resource information, or other relevant information. |
Download the WBS Dictionary Template in word format: WBS DICTIONARY