Method Statement for Wood Door Installation
Article Summary: wooden doors installation method statement includes the following:
- Non-fire-rated, semi-solid-core wooden doors.
- Non-fire-rated, semi-solid-core, custom-fabricated wooden doors and access doors.
- Wood veneer, solid hardwood raised panels, and stained varnish.
- Materials for application.

1. Delivery, storage, and handling of wooden doors
- Store doors in clean dry ventilated areas. Stack doors flat and off floors, supported to prevent wharfing. No other materials are to be placed on top of stacked doors.
- All doors will be packed with plastic and cardboard protection to the edges.
- Store flat over level surface above the floor on wood blocks.
- Each door and frame is tagged with a sticker indicating the door number and location.
- All doors and frames delivered with finished factory painting final touch will be at the site before handing over.
2. Installation of wooden doors
- Check the tagged doors and locate them as per the approved shop drawing and door schedule.
- Verify opening dimensions, angles, and levels from finish floor line reference to ensure that frames fit the openings. Align and fit the door in the frame to each desired location and elevation.
- Fix door frames by anchor bolts located as per approved shop drawings and to be covered by wood caps later.
- Install, align, and fit the doors in frames with uniform clearance and bevel to provide 3mm at heads, jambs, and between pairs of doors as per approved shop drawings.
- Architraves will be fixed with nails and to be covered by wood putty. All surrounding gaps will be filled with silicone.
- Completed wooden doors shall operate freely and smoothly without rattle or bound condition.
- Clean stains and traces of cleaning fluid.

Ready to take your skills to the next level? 🚀 Check out our Special Online Courses! 🚀
Gain valuable insights, boost your career, and learn from industry experts.
Construction Project Management Fundamentals Course
Learn how real construction projects are planned, managed, and controlled — from initiation to closing — using practical methods to deliver on…
- 8,016 students
- WhatsApp support group
- Certificate
3. Adjusting and protecting wooden doors
- Protect doors as recommended by the manufacturer to ensure that wooden doors are without damage or deterioration at the time of substantial completion.
- Replace doors that do not swing or operate freely.
- Replace doors that are damaged during installation.

4. Doors installation cost
The cost breakdown for door installation can vary depending on numerous factors, including the type of door, labor rates in your area, additional features, and materials required. Here’s an overall breakdown of the components that contribute to door installation costs:
- Cost of the Door: The type and quality of the door you choose will significantly influence the overall cost. Doors can range from basic interior doors to high-end custom exterior doors.
- Labor Costs: Labor costs will depend on the installation’s complication, the labor’s skill level, and local labor rates. This includes procedures such as removing the old door, installing the new door, and any modifications needed for a proper fit.
- Hardware and Accessories: This includes items like hinges, doorknobs, locks, handles, and other hardware. Higher-quality or particular hardware can increase costs.
- Preparation and Finishing: Depending on the type of door and the condition of the opening, there might be additional work needed, such as adjusting the door frame, trimming, painting or staining, and adding weatherstripping.
- Weatherproofing and Sealing: Exterior doors mostly require weatherproofing measures to prevent drafts and water infiltration. This could include caulking and insulation.
- Special Features: If you’re installing a specific door with features like windows, sidelights, or decorative glass, these can significantly increase the cost.
- Location: Labor and material costs can vary based on your geographical location and the local cost of living.
Download the Resources of this Article
Method Statement for Wood Door Installation 392.06 KB 4591 downloads
Keep growing with Planning Engineer
Learn with a clear path
From Primavera P6 basics to claims, cost control and Power BI. Start with our free courses.
Browse coursesGet help on WhatsApp
Every course comes with a private WhatsApp support group where our team answers your questions.
Join a courseFind planning jobs
68 open planning and project control jobs. Post your resume so employers can find you.
See jobsGet tips by email
Free planning tips, templates and course offers. Unsubscribe any time.







![What Is Included in the Weekly Report [Report Template]](https://planningengineer.net/wp-content/uploads/2025/05/What-Is-Included-in-the-Weekly-Report-Report-Template-600x400.png)