Materials Procurement Scheduling in a Baseline Programme
Materials tracking is very important to project success. in this post I will show you how to create Materials Procurement Scheduling in a Baseline Programme to track the materials as per the following sequence:
1- Material Submittal
2- Material Approval
3- PO Issued
4- Delivery Period

Data Management and Reporting
Data Management is the key success of construction projects reporting. This self-study course will teach you using a step by step case…
- 1,674 students
- WhatsApp support group
- Certificate
5- Manufacture Started
6- Shipment Date
7- Customs Clearance
8- Delivery to Site / Store
Watch the Lesson video:
Download the Resources of this Article
Procurement Tracking Log 148.29 KB 16161 downloads
Keep growing with Planning Engineer
Learn with a clear path
From Primavera P6 basics to claims, cost control and Power BI. Start with our free courses.
Browse coursesGet help on WhatsApp
Every course comes with a private WhatsApp support group where our team answers your questions.
Join a courseFind planning jobs
25 open planning and project control jobs. Post your resume so employers can find you.
See jobsGet tips by email
Free planning tips, templates and course offers. Unsubscribe any time.







![_Can We Change a Relationship While Updating a Time Schedule How and Why [Change Log Template]](https://planningengineer.net/wp-content/uploads/2025/04/Can-We-Change-a-Relationship-While-Updating-a-Time-Schedule-How-and-Why-Change-Log-Template-600x400.png)