
How to Filter Delayed Activities in Primavera
In this article, we will be providing you with how to filter the activities that have actual performance percentages less than the scheduled percentages.
First of all, you need to assign a baseline to your project by clicking on “Maintain baselines” from the “Projects” tab and choosing your baseline, then click on “Assign baselines” from the same tab and choose your baseline once again.
Once the baseline is assigned to your project, schedule your project on the day that you want to filter your activities based on.
Show the Wanted Columns
From “columns”, choose “Schedule % complete” and “Activity % complete”. Schedule % complete: represents the percentage of the work that should be done by the date of the schedule for each activity (planned %). Activity % complete: represents the percentage of the actual work done by the date of the schedule for each activity. To know whether there is a delay in the activities or not, we need to create a column that plots the difference between the planned % and the actual %, so we are going to create a new column called “Variance %”.
This is how the “Variance %” works if it is positive it means you are ahead in this activity and if it is negative it means it is a Delayed Activity. 
The steps to create a new column are:
- Go to “Enterprise”.
- choose “User Defined Fields”.
- then “Add” and name the new element as “ Variance % ” and choose the type “Number”.
- From “Tools”, choose “Global change”, then click “New”.
- click “Add” to create the equation of the column “Variance %”.
- The equation is as follows:
- Click “Change” then click “Commit Changes” to save the changes.
- Now the Column of “Variance %” is ready and you can see the Delayed Activities.
- From “Columns” Show the “Variance %” Column.

Now you can make a filter to just filter the Delayed Activities only from this time schedule.
The applied filter will show the activities with a negative “variance%”, as per the equation of “variance%”, negative results indicate that the scheduled % of the activity is bigger than the actual %.
All the activities that show up are the delayed ones that you must handle to get the schedule back on track.
For the final presentation using Excel, you can use our tool “From Primavera to Excel” to maintain the WBS of the activities and provide a better representation of the activities. If you are interested in EOT Claims and delays analysis, check this course: Claims Management (EOT) Course
The Filter for the Delayed Activities
- From “Filters”, “Variance %” is less than 0.
All the activities that show up are the delayed ones that you must handle to get the schedule back on track.For the final presentation using Excel, you can use our tool “From Primavera to Excel” to maintain the WBS of the activities and provide a better representation of the activities. If you are interested in EOT Claims and delays analysis, check this course: Claims Management (EOT) Course
Download the Resources of this Article
How to Filter Delayed Activities in Primavera 1.01 MB 1333 downloads
This File is included in the following course(s)
Keep growing with Planning Engineer
Learn with a clear path
From Primavera P6 basics to claims, cost control and Power BI. Start with our free courses.
Browse coursesGet help on WhatsApp
Every course comes with a private WhatsApp support group where our team answers your questions.
Join a courseFind planning jobs
25 open planning and project control jobs. Post your resume so employers can find you.
Ready to take your skills to the next level? 🚀 Check out our Special Online Courses! 🚀
Gain valuable insights, boost your career, and learn from industry experts.
Get tips by email
Free planning tips, templates and course offers. Unsubscribe any time.









