    • BORED PILING METHOD STATEMENT

    BORED PILING METHOD STATEMENT

    • Posted by Hany Ismail, MSC, PMP
    • Categories Management Template, Planning Discussions
    • Date February 7, 2014
    • Comments 0 comment

    BORED PILING METHOD STATEMENT.

    WORK PROCEDURE

    PROJECT:

    Ref No. FOUN/04

    PAGE 1 OF 2

    SECTION:

    FOUNDATIONS

    DATE OF ISSUE

    Dec 2012

    SUBJECT:

    BORED PILING

    BY:

    QA/QC ENGINEER

    APPROVED BY:

    QEHS MANAGER

    ACTION

    VERIFY

    1.    SCOPE

    The scope of this procedure covers the control of installation of Bored Cast-in-Situ Concrete piles executed by a sub-contractor.

    2.    PROCEDURE

    .1    Method Statement:

    A method statement shall be submitted by the piling Sub-contractor for approval which shall include:

    i)    Construction procedure.

    ii)    Pile design with calculations.

    iii)    Testing procedure.

    iv)    Documentation to be maintained during the execution of work.

    v)    Mix design for concrete.

    vi)    Specification for reinforcement steel and bentonite clay.

    vii)    Any other information required by the specification.

    .2    Construction Programme:

    The sub-contractor shall submit a programme for approval based on the Contract Programme. The subcontractor shall also indicate the mobilisation time of plant, equipment, materials and work force.

    .3    Piling Sequence:

    Approval of piling sequence will be given prior to commencement of piling by the Subcontractor.

    .4    Setting-Out:

    HEE will execute pre-piling setting out and offer for cross-checking by Subcontractor’s Surveyor and Consultant’s Representative.

    Project

    Manager

    Sub-contractor

    Project

    Manager

    Subcon/

    FCC Surveyor

    Method

    Statement

    Approved

    Construction Programme

    Approval

    Field Book

    WORK PROCEDURE

    PROJECT:

    Ref No. FOUN/04

    PAGE 2 OF 2

    SECTION:

    FOUNDATIONS

    DATE OF ISSUE

    Dec 2012

    SUBJECT:

    BY:

    QA/QC ENGINEER

    BORED PILING

    APPROVED BY:

    QHSE MANAGER

    ACTION

    VERIFY

    .5    Source Certificates:

    Reinforcement steel and Bentonite test certificates if required shall be obtained from the Subcontractor and, submitted for approval by the Consultant.

    .6    Concrete Cube Testing:

    Cube results will be assessed and retained. The cube test reports shall be clearly identified with the location of pour by reference to the checksheet.

    .7    Testing of Piles:

    The Subcontractor shall carry out a load test and integrity test as specified in the Contract.

    .8    Inspection of Work/Checksheet:

    The work shall be inspected using the attached checksheet as Appendix FOUN/04/A which shall be completed as verification and record of compliance.

    .9    Non-Conformity:

    Non-conforming workmanship shall be notified to the Subcontractor as Appendix 7/3/6/A and corrective action taken in accordance with good working practice and Consultants approval.

    Project Engineer

    Project Engineer/

    Labtech.

    Subcon.

    QA/QC

    QA/QC

    Source certificate

    Test result, FOUN/04/A

    Pile testing record

    Checksheet

    Non-

    Conformity Report

    PROJECT:                        SITE NO.:

    CHECK SHEET FOR BORED PILING

    Sheet No.

    SUBCONTRACTOR: FATAYERJI

    SECTION OF WORK ____________________________LOCATION _________________

    STAGE

    ITEM

    Checked

    by

    DATE

    PREPARATION 1. Subcontractor’s method statement approved. PE
    2. Materials approved by the consultant. PE
    3. Cross-check location of Pile. SU
      APPROVAL TO PROCEED QA/QC
    INSTALLATION 4. Check borehole to be filled with Bentonite
    slurry at all times.
    GF  
    5. Check cleaning of bottom of borehole. GF
    6. Check reinforcement cage. SE
    7. Check minimum cover while lowering cage into the borehole. GF  
    8. Check slump of concrete. Lab
    9. Check cut-off level + location. SU
    APPROVAL TO PROCEED WITH PILE CAP. CM

    CM – Construction Manager, QA/QC – Quality Assurance/Quality Control, PE – Project Engineer, SE – Site Engineer, GF – General Foreman, SU – Surveyor, Lab – Laboratory Technician

    DOWNLOAD BORED PILING METHOD STATEMENT WORD TEMPLATE: BORED PILING

    Tag:BORED, bored piling, construction programme, METHOD, method statement, PILING, piling method, procedure project, project engineer, project manager, statement

    • Share:
    Hany Ismail, MSC, PMP
    Hany Ismail, MSC, PMP

    Hany Ismael is the founder and CEO of Planning Engineer Est. in Egypt. He has started his career back in 2003 as a site engineer, technical office engineer, planning engineer, planning manager, and finally planning department manager where he has been involved in several mega construction projects in Egypt and Saudi Arabia. In 2016, he established his own company in Egypt “Planning Engineer Est.” Hany gained his MSc degree in project management from Liverpool University-UK 2013-2016, PMP certified from PMI-USA 2010, and BSc Civil Engineer Tanta University-Egypt 2003. Hany provided more than 3,500 hours of planning and project management training on his website planningengineer.net, YouTube channel, and offline courses since 2011. He enjoys teaching project management in simple and practical way, and he developed several planning tools, techniques and courses.

    Previous post

    Excavation, Earthwork and Filling Method Statement
    February 7, 2014

    Next post

    Batching Of Concrete Method Statement
    February 8, 2014

    You may also like

    EOT without approved Baseline
    EOT without approved Baseline
    30 June, 2022
    2022-06-19_11-56-47
    Sample Weekly and Monthly Reports
    20 June, 2022
    How to become a planning engineer
    How to be prepared to work as a junior planning engineer?
    22 May, 2022

    Leave A Reply Cancel reply

    You must be logged in to post a comment.

    Cart

    0

    Planning Courses

    Cost Control for Construction Projects

    Cost Control for Construction Projects

    $299.00
    Power Bi Monitoring and Controlling with P6

    Power Bi Monitoring and Controlling with P6

    $299.00
    Advanced Planning 3 Courses Package

    Advanced Planning 3 Courses Package

    $499.00
    Data Management and Reporting

    Data Management and Reporting

    $199.00
    Primavera Online Basic Course -Arabic

    Primavera Online Basic Course -Arabic

    $99.00
    Professional Planning Engineer (PPE)

    Professional Planning Engineer (PPE)

    $335.00
    Claims Management and (EOT)

    Claims Management and (EOT)

    $175.00
    Primavera Online Basic Course -English

    Primavera Online Basic Course -English

    $99.00

    Follow Us:

    About Us | Contact Us | Terms of Service | Privacy Policy | Refund Policy

    Copyright ©2012- 2018 planningengineer.net | All materials, unless otherwise noted, were developed originally for Planning Engineer Website. In the event that there is still a problem or error with copyrighted material, the break of the copyright is unintentional and noncommercial and the material will be removed immediately upon presented proof.

    • Planning Courses
    • Planning Jobs
    • Planning Blog
    Posting....