Primavera P6 Reflection
Today we are going to talk about one of Primavera P6 features, which will help you as a planning or scheduler it is “Reflection”.
Reflection is a unique tool that you can use instead of copying a project and checking different scenarios over it with different changes or scenarios.
To easily understand the reflection tool, you can check the following:
Ready to take your skills to the next level? 🚀 Check out our Special Online Courses! 🚀
Gain valuable insights, boost your career, and learn from industry experts.
- Create Reflection
- Make Changes to the Reflection
- Merge Changes Back to the Source Project
Reflections offer a much broader range of capabilities than those envisaged by its, Using Reflections for what-if analysis. Briefly, Reflection allows you to save a linked copy of a project, update it, and then merge those changes back into the original project. But that’s not all you can do with it.
Simply it is a copy of your project with a link to the project source, also you can merge all the changes or updates you have done in the reflection project to your source project and show all the changes within your reflection, and the committee our ignore these changes.
Steps to create reflection and merge changes:
Step 1:
Go to the Main Projects menu, Select, and highlight the project that you are interested in, and right-click on it to select “Create Reflection…”:

Step 2:
If your project has assigned baseline he asked to add or not “Click Ok”.

Step 3:
You can check the reflection, and source project columns making changes and merging them. Take note of the yellow question mark attached to the folder icon, representing that this is a reflection and not the source file.

Step 4:
Make changes or updates on the reflection.
We changed the duration of two activities, which in turn moved out the end date for completion of the project.

Primavera Online Basic Course -English
Online Primavera P6 Course for Engineers & Construction Managers Learn how to use Oracle Primavera P6 to plan, schedule, monitor, and control…
- 5,625 students
- WhatsApp support group
- Certificate

Step 5:
Merge the changes to the source project, right-click on the reflection project, and select “Merge Reflection into Source Project…”:
We now want to compare the project changes and update the Project Team, so we need to create a printing reflection difference report to compare and view the modifications. Go back to the Main Projects menu,

Step 6:
The Preview Changes box that provides the comparison between the reflection’s changes and the source schedule.
Under “Before merging”, mark the appropriate checkbox. You can choose one or both options.
Check the “Create a copy of the source project…as a baseline” if you want to create a baseline in the source project with the name of the project.
Check the “Create a backup file (.xer) of source project…” if you want to export the project as a. XER file (you must choose the export location).

In this example, you can see where the changes were made to the durations of the two activities. Primavera P6 allows you to select the changes that you want to bring over to the source project. In this case, we will check all the updates and select “Merge Changes”:

Additionally, you must determine the actions that Primavera P6 should take after merging. The three options include keeping the reflection after the merge, deleting the reflection after the merge, or replacing the reflection with an updated reflection from the source data following the merge.

After the merge, a confirmation will appear:

Next, open the source project and you can see the updates to the durations of the two activities. Use the F9 key or re-schedule your project and see that the dates have moved out as previously agreed to by the Project Team:

LIMITATIONS WITH USING REFLECTIONS
There are some limitations when it comes to creating and using reflections in Primavera P6 and integrating them into the source project.
Manual updates become necessary in certain scenarios. For instance, the source file is unable to differentiate between deletions and additions within the project. While adding new WBS elements and tasks is successful, the system fails to recognize deletions of existing WBS elements and tasks.
Primavera P6 issues a warning when attempting to merge a deleted section of the reflection into the source project. Beyond WBS elements and tasks, various items such as relationships, resource assignments, expenses, risks, and issues will not be removed from the source project if deleted in the reflection project.
Note that modifications to Project/Activity/Resource/Role IDs, price/unit, and cost accounts may lead to duplicate entries in the source project. For example, updating the Activity ID in a task will result in the task being duplicated as a new entry in the source project once the reflection is merged. In such cases, Primavera P6 users should manually update the source project.
Download the Resources of this Article
Primavera P6 Reflection 927.78 KB 965 downloads
Keep growing with Planning Engineer
Learn with a clear path
From Primavera P6 basics to claims, cost control and Power BI. Start with our free courses.
Browse coursesGet help on WhatsApp
Every course comes with a private WhatsApp support group where our team answers your questions.
Join a courseFind planning jobs
110 open planning and project control jobs. Post your resume so employers can find you.
See jobsGet tips by email
Free planning tips, templates and course offers. Unsubscribe any time.
Leave A Reply
You must be logged in to post a comment.










1 Comment
thank you very much