    Free PSP 100 Exam Questions

    • Posted by Hany Ismail, MSC, PMP
    • Categories Project Management
    • Date October 29, 2016
    • Comments 4 comments

    What is PSP Certificate?

    Planning & Scheduling Professional Certificate is an international certificate that you can get through the “AACE”, PSP Certificate validates the planning and scheduling engineers skills to the international practices standards in project planning and scheduling.

    PSP Requirements:

    You need 4 years of experience and Collage/University Degree (such as Engineering, Building Construction, Architecture, Computer Science, etc.).
    OR 8 years of professional experience.
    And you need a copy of experience and education certificates as evidence when applying.

    100 Practise Exam Questions:

    Below are 100 questions for your practise. You can see the answer of any question immediately, or you can save the exam and resume it later on. Finally, when you finish the exam, your results will show immediately and you will receive an emil with the questions, your answer and the correct answer.


    You can take This Exam Now.

     1%

    Question 1 of 98

    1. P.1 Which of the following is generally the MOST correct use of a project network diagram?
     
     
     
     

    Question 1 of 98

    Loading... Loading…

    Question 2 of 98

    2. P.2 At a minimum, periodic forecasts must be done at what interval?
     
     
     
     

    Question 2 of 98

    Loading... Loading…

    Question 3 of 98

    3. P.3 The calculated duration for a project is 28.166. The standard deviation is 5.5. What technique would you use to compute the probability of completing a project on a specific day?
     
     
     
     

    Question 3 of 98

    Loading... Loading…

    Question 4 of 98

    4. P.4 The best reason to use multiple calendars is to ___________
     
     
     
     

    Question 4 of 98

    Loading... Loading…

    Question 5 of 98

    5. P.5 During planning you discover that the time needed to complete the project is longer than the time available. What do you do?
     
     
     
     

    Question 5 of 98

    Loading... Loading…

    Question 6 of 98

    6. P.6 Free float is the ____________
     
     
     
     

    Question 6 of 98

    Loading... Loading…

    Question 7 of 98

    7. P.7 In an activity-on-arrow diagram, the boxes represent:
     
     
     
     

    Question 7 of 98

    Loading... Loading…

    Question 8 of 98

    8. P.8 Every activity in a schedule, except the first and last activity, should have activity as a successor
     
     
     
     

    Question 8 of 98

    Loading... Loading…

    Question 9 of 98

    9. P.9 A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What tool is BEST described here?
     
     
     
     

    Question 9 of 98

    Loading... Loading…

    Question 10 of 98

    10. P.10 An early start constraint dictates __________
     
     
     
     

    Question 10 of 98

    Loading... Loading…

    Question 11 of 98

    11. P.11 Dummy activities are NOT used on which type of network diagram?
     
     
     
     

    Question 11 of 98

    Loading... Loading…

    Question 12 of 98

    12. P.12 Which of the following is NOT required when performing weekly or monthly schedule updates?
     
     
     
     

    Question 12 of 98

    Loading... Loading…

    Question 13 of 98

    13. P.13 During the creation of a project plan, you want to find the critical path of the project. Which of the following project management tools would you use to determine the critical path?
     
     
     
     

    Question 13 of 98

    Loading... Loading…

    Question 14 of 98

    14. P.14 All of the following describe the critical path of a schedule except:
     
     
     
     

    Question 14 of 98

    Loading... Loading…

    Question 15 of 98

    15. P.15 How many types of relationships between activities can be found on a precedence diagram?
     
     
     
     

    Question 15 of 98

    Loading... Loading…

    Question 16 of 98

    16. P.16 Project delays are best analyzed ________
     
     
     
     

    Question 16 of 98

    Loading... Loading…

    Question 17 of 98

    17. P.17 All of the following relate to controlling the schedule EXCEPT?
     
     
     
     

    Question 17 of 98

    Loading... Loading…

    Question 18 of 98

    18. P.18 Hammock activities in a schedule include all of the following except that they
     
     
     
     

    Question 18 of 98

    Loading... Loading…

    Question 19 of 98

    19. P.19 A project manager is involved in the ABC project. Time lines have slipped for project ABC and he feels there could have been a mistake in the initial time estimate of this project. The following are assumptions that he made when doing the initial schedule using the critical path method (CPM). Which one is incorrect?
     
     
     
     

    Question 19 of 98

    Loading... Loading…

    Question 20 of 98

    20. P.20 Which of the following is NOT required while initially planning a project?
     
     
     
     

    Question 20 of 98

    Loading... Loading…

    Question 21 of 98

    21. P.21 Project schedules help control all of the following except for
     
     
     
     

    Question 21 of 98

    Loading... Loading…

    Question 22 of 98

    22. P.22 During the planning phase, Task G was estimated to take five days. Task G is on the critical path. On day two, it became clear that Task G would take 15 days, which will impact the imposed project end date. The project team meets to perform root cause analysis to identify the cause of the variance and to plan schedule recovery with activities performed later in the schedule. What should be the output of this meeting?
     
     
     
     

    Question 22 of 98

    Loading... Loading…

    Question 23 of 98

    23. P.23 The calculation of the latest finish time and latest start time for all incomplete network activities or late time for events in the ADM and PDM scheduling methods is referred to as ______
     
     
     
     

    Question 23 of 98

    Loading... Loading…

    Question 24 of 98

    24. P.24 Which of the following are GENERALLY illustrated better by bar charts than network diagrams?
     
     
     
     

    Question 24 of 98

    Loading... Loading…

    Question 25 of 98

    25. P.25 In an earned value-based system, a schedule performance index of less than one for the project indicates the project is ____________
     
     
     
     

    Question 25 of 98

    Loading... Loading…

    Question 26 of 98

    26. P.26 You evaluate your critical path and determine the project will be completed two weeks ahead of management’s expected due date. What should you do?
     
     
     
     

    Question 26 of 98

    Loading... Loading…

    Question 27 of 98

    27. P.27 An earned value-based project control system can use either of which two budgets as the basis of its calculations? feet or dollars
     
     
     
     

    Question 27 of 98

    Loading... Loading…

    Question 28 of 98

    28. P.28 While evaluating the Gantt chart, the project manager determines that the project is behind schedule. What should she do?
     
     
     
     

    Question 28 of 98

    Loading... Loading…

    Question 29 of 98

    29. P.29 If the optimistic estimate is one, the pessimistic estimate is nine, and the most likely estimate is eight, what is the PERT estimate?
     
     
     
     

    Question 29 of 98

    Loading... Loading…

    Question 30 of 98

    30. P.31 The project manager has a project that is three months behind but, surprisingly, markedly under budget. She has decided to try to make up time, but wants to avoid rework. What should she do?
     
     
     
     

    Question 30 of 98

    Loading... Loading…

    Question 31 of 98

    31. P.32 A total float value less than zero on a schedule activity indicates that the
     
     
     
     

    Question 31 of 98

    Loading... Loading…

    Question 32 of 98

    32. P.33 During schedule development, which of the following would BEST provide the basis for the most likely activity duration estimate?
     
     
     
     

    Question 32 of 98

    Loading... Loading…

    Question 33 of 98

    33. P.34 Total float is defined as the amount of time an activity can be delayed without impacting _______
     
     
     
     

    Question 33 of 98

    Loading... Loading…

    Question 34 of 98

    34. P.35 What is the duration of a milestone?
     
     
     
     

    Question 34 of 98

    Loading... Loading…

    Question 35 of 98

    35. P.36 When creating a baseline project schedule, the ideal outcome is ___________
     
     
     
     

    Question 35 of 98

    Loading... Loading…

    Question 36 of 98

    36. P.37 A project manager received executive orders to deliver the project two weeks earlier than scheduled doing whatever it takes. He decided the least costly means would be to add resources to critical path tasks in order to shorten the time of those tasks. In this case, the project manager has:
     
     
     
     

    Question 36 of 98

    Loading... Loading…

    Question 37 of 98

    37. P.38 What is a critical path method schedule? accomplished by responsible party and when it is to be accomplished
     
     
     
     

    Question 37 of 98

    Loading... Loading…

    Question 38 of 98

    38. P.39 You are managing the project when you discover an estimated completion date will occur after the desired date. What should you do FIRST?
     
     
     
     

    Question 38 of 98

    Loading... Loading…

    Question 39 of 98

    39. P.40 What is the result of a forward pass calculation?
     
     
     
     

    Question 39 of 98

    Loading... Loading…

    Question 40 of 98

    40. P.41 Which of the following BEST describes comparing actual dates with planned dates?
     
     
     
     

    Question 40 of 98

    Loading... Loading…

    Question 41 of 98

    41. P.42 A project plan results in a project schedule that is too long. If the project network diagram cannot change but you have extra personnel resources, what should you do?
     
     
     
     

    Question 41 of 98

    Loading... Loading…

    Question 42 of 98

    42. P.43 Resource planning must take all of the following into account except for
     
     
     
     

    Question 42 of 98

    Loading... Loading…

    Question 43 of 98

    43. P.44 After analyzing the status of your project, you determine that the earned value is lower than the planned value. What should you expect as an outcome if this trend continues?
     
     
     
     

    Question 43 of 98

    Loading... Loading…

    Question 44 of 98

    44. P.45 Which of the following describes a type of schedule logic?
     
     
     
     

    Question 44 of 98

    Loading... Loading…

    Question 45 of 98

    45. P.46 The sponsor wants the project completed in 40 days. The CPI is 1.1, the project critical path duration is 38 days with a standard deviation of two days. What is the maximum project float?
     
     
     
     

    Question 45 of 98

    Loading... Loading…

    Question 46 of 98

    46. P.47 Hard logic within a CPM schedule refers to activities ___________
     
     
     
     

    Question 46 of 98

    Loading... Loading…

    Question 47 of 98

    47. P.48 A project manager obtains weighted average duration estimates from the team to calculate activity duration. Which type of mathematical analysis is he using?
     
     
     
     

    Question 47 of 98

    Loading... Loading…

    Question 48 of 98

    48. P.49 What is the primary difference between the arrow diagramming method (ADM) and precedence diagramming method (PDM)?
     
     
     
     

    Question 48 of 98

    Loading... Loading…

    Question 49 of 98

    49. P.50 A heuristic is BEST described as a:
     
     
     
     

    Question 49 of 98

    Loading... Loading…

    Question 50 of 98

    50. P.51 A task needs more time and the project manager determines that there is enough reserve to accommodate the change. Who needs to approve the change?
     
     
     
     

    Question 50 of 98

    Loading... Loading…

    Question 51 of 98

    51. P.53 You have a project with the following tasks: Task A takes 40 hours and can start after the project starts. Task B takes 25 hours and should happen after the project starts. Task C must happen after Task A and takes 35 hours. Task D must happen after Tasks B and C and takes 30 hours. Task E must take place after Task C and takes 10 hours. Task F takes place after Task E and takes 22 hours. Which of the following is TRUE if Task B actually takes 37 hours?
     
     
     
     

    Question 51 of 98

    Loading... Loading…

    Question 52 of 98

    52. P.54 Longest path is identified by using ________
     
     
     
     

    Question 52 of 98

    Loading... Loading…

    Question 53 of 98

    53. P.55 If project time and cost are not as important as the number of resources used each month, which of the following is the BEST course of action?
     
     
     
     

    Question 53 of 98

    Loading... Loading…

    Question 54 of 98

    54. P.56 A project deadline has been imposed for the end of the year. The project consists of two tasks. Task A has a duration of two months and task B has a duration of three months. Tasks A and B can be performed concurrently. The start date for the project is set for the beginning of July. What is the total duration for the critical path?
     
     
     
     

    Question 54 of 98

    Loading... Loading…

    Question 55 of 98

    55. P.57 A task has an early start of day 3, a late start of day 13, an early finish of day 9, and a late finish of day 19. The task:
     
     
     
     

    Question 55 of 98

    Loading... Loading…

    Question 56 of 98

    56. P.58 Which of the following is NOT a construction planning activity?
     
     
     
     

    Question 56 of 98

    Loading... Loading…

    Question 57 of 98

    57. P.59 Which of the following is NOT correct about network diagrams?
     
     
     
     

    Question 57 of 98

    Loading... Loading…

    Question 58 of 98

    58. P.60 What is the BEST method of estimating the time for a task that has never been done by your company before?
     
     
     
     

    Question 58 of 98

    Loading... Loading…

    Question 59 of 98

    59. P.61 What is a prerequisite if schedule status is to be summarized using an earned value-based system?

    Question 59 of 98

    Loading... Loading…

    Question 60 of 98

    60. P.62 According to your project network diagram, the critical path for the project is six weeks. One week into the project, the project sponsor informs you that the executive steering committee has moved the project’s finish date to two weeks sooner than your published finish date. Assuming you are on schedule, what is the project slack?
     
     
     
     

    Question 60 of 98

    Loading... Loading…

    Question 61 of 98

    61. P.63 When resource leveling craft labor for a critical path schedule, the scheduler ___________
     
     
     
     

    Question 61 of 98

    Loading... Loading…

    Question 62 of 98

    62. P.64 All of the following are inputs to schedule development EXCEPT?
     
     
     
     

    Question 62 of 98

    Loading... Loading…

    Question 63 of 98

    63. P.65 Free slack is the amount of time a task can be delayed without delaying the:
     
     
     
     

    Question 63 of 98

    Loading... Loading…

    Question 64 of 98

    64. P.66 A task has an early start of day three, a late start of day 13, an early finish of day nine, and a late finish of day 19. What is the duration of this task?
     
     
     
     

    Question 64 of 98

    Loading... Loading…

    Question 65 of 98

    65. P.67 Which best describes the following: A master schedule is composed of five different, logically tied subproject schedules. How many different critical paths can be found?
     
     
     
     

    Question 65 of 98

    Loading... Loading…

    Question 66 of 98

    66. P.68 A project has three critical paths. How does this affect the project?
     
     
     
     

    Question 66 of 98

    Loading... Loading…

    Question 67 of 98

    67. P.69 Which of the following will NOT affect the total float calculation?
     
     
     
     

    Question 67 of 98

    Loading... Loading…

    Question 68 of 98

    68. P.70 Which of the following is the BEST tool for showing the team the project schedule status during project execution?
     
     
     
     

    Question 68 of 98

    Loading... Loading…

    Question 69 of 98

    69. P.71 You are a project manager for a new product development project that has four levels in the work breakdown structure, and has been sequenced using the arrow diagramming technique. The activity duration estimates have been received. What time management activity would you do NEXT?
     
     
     
     

    Question 69 of 98

    Loading... Loading…

    Question 70 of 98

    70. P.72 In a graphical earned value analysis, what time-scaled value is the indicator that is used to represent both schedule and cost performance?
     
     
     
     

    Question 70 of 98

    Loading... Loading…

    Question 71 of 98

    71. P.73 During project execution, the forecast remaining hours begin to exceed planned remaining hours. Consequently, the project takes on a negative variance. Which analysis method is the project manager likely to use as a measurement tool to validate this information?
     
     
     
     

    Question 71 of 98

    Loading... Loading…

    Question 72 of 98

    72. P.74 The slack of a task is determined by:
     
     
     
     

    Question 72 of 98

    Loading... Loading…

    Question 73 of 98

    73. P.75 Which of the following is NOT an element of the project planning process?
     
     
     
     

    Question 73 of 98

    Loading... Loading…

    Question 74 of 98

    74. P.76 A project has seven activities: A, B, C, D, E, F, and G. A, B, and D can start anytime. A takes three weeks, B takes five weeks, and D takes 11 weeks. A and B must be completed before C can start. C takes six weeks. B, C, and D must be completed before E can start. E takes two weeks. F can start as soon as C is completed and requires four weeks. E must be completed before G can start. G takes three weeks. F and G must be completed for the project to be completed. What activities have slack available?
     
     
     
     

    Question 74 of 98

    Loading... Loading…

    Question 75 of 98

    75. P.77 A driving relationship is __________
     
     
     
     

    Question 75 of 98

    Loading... Loading…

    Question 76 of 98

    76. P.78 To control the schedule, a project manager is re-analyzing the project to predict project duration. She does this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using?
     
     
     
     

    Question 76 of 98

    Loading... Loading…

    Question 77 of 98

    77. P.79 If after calculating a schedule an activity exhibits negative total float, which of the following is certain. The activity _________
     
     
     
     

    Question 77 of 98

    Loading... Loading…

    Question 78 of 98

    78. P.80 What is the BEST report to use when reporting to senior management?
     
     
     
     

    Question 78 of 98

    Loading... Loading…

    Question 79 of 98

    79. P.81 Which of the following BEST describes the primary use of project management software?
     
     
     
     

    Question 79 of 98

    Loading... Loading…

    Question 80 of 98

    80. P.82 A team member from research and development tells you that her work is too creative to provide you with a fixed single estimate for the task. You both decide to use the average time the task has taken for past projects to predict the future. This is an example of which of the following?
     
     
     
     

    Question 80 of 98

    Loading... Loading…

    Question 81 of 98

    81. P.83 Which of the following will always describe the critical path? The path with
     
     
     
     

    Question 81 of 98

    Loading... Loading…

    Question 82 of 98

    82. P.84 A project manager for a small construction company has a project that was budgeted for US $130,000 over a six week period. According to her schedule, the project should have cost US $60,000 to date. However, it has cost US $90,000 to date. The project is also behind schedule, because the original estimates were not accurate. Who has the primarily responsibility to solve this problem?
     
     
     
     

    Question 82 of 98

    Loading... Loading…

    Question 83 of 98

    83. P.85 You are looking at the standard reports that the project office has supplied, and you see network diagrams and Gantt charts. Under what circumstances would you want to use a network diagram instead of a Gantt chart?
     
     
     
     

    Question 83 of 98

    Loading... Loading…

    Question 84 of 98

    84. P.86 Under what circumstances should one use resource-leveling calculations?
     
     
     
     

    Question 84 of 98

    Loading... Loading…

    Question 85 of 98

    85. P.87 Which estimating method uses one time estimate for each task?
     
     
     
     

    Question 85 of 98

    Loading... Loading…

    Question 86 of 98

    86. P.88 A task has an early start of day three, a late start of day 13, an early finish of day nine, and a late finish of day 19. What is the task’s float?
     
     
     
     

    Question 86 of 98

    Loading... Loading…

    Question 87 of 98

    87. P.89 In its simplest form, what is the main drawback of critical path method scheduling?

    Question 87 of 98

    Loading... Loading…

    Question 88 of 98

    88. P.90 You are a project manager for a small construction project. Your project was budgeted for US $72,000 over a six-week period. As of today, you’ve spent US $22,000 of your budget to complete work that you originally expected to cost US $24,000. According to your schedule, you should have spent US $30,000 by this point. Based on these circumstances, your project could be BEST described as:
     
     
     
     

    Question 88 of 98

    Loading... Loading…

    Question 89 of 98

    89. P.91 Which of the following is correct concerning a change control system?
     
     
     
     

    Question 89 of 98

    Loading... Loading…

    Question 90 of 98

    90. P.92 The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it __________
     
     
     
     

    Question 90 of 98

    Loading... Loading…

    Question 91 of 98

    91. P.93 A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. A takes three weeks, B takes five weeks, and D takes 11 weeks. A and B must be completed before C can start. C requires six weeks to complete. B, C, and D must be completed before E can start. E requires two weeks. F takes four weeks and can start as soon as C is completed. E must be completed before G starts. G requires three weeks. F and G must be completed for the project to be completed. What is the critical path?
     
     
     
     

    Question 91 of 98

    Loading... Loading…

    Question 92 of 98

    92. P.94 If the optimistic estimate for a task is 12 days and the pessimistic estimate is 18 days, what is the standard deviation of the task?
     
     
     
     

    Question 92 of 98

    Loading... Loading…

    Question 93 of 98

    93. P.95 Which of the following is true of activity duration estimating?
     
     
     
     

    Question 93 of 98

    Loading... Loading…

    Question 94 of 98

    94. P.96 You have a project with four tasks as follows: Task 1 can start immediately and has an estimated duration of one. Task 2 can start after task 1 is completed and has an estimated duration of four. Task 3 can start after Task 2 is completed and has an estimated duration of five. Task 4 can start after Task 1 is completed and must be completed when Task 3 is completed. The estimate for Task 4 is ten. What is the shortest amount of time in which the project can be completed?
     
     
     
     

    Question 94 of 98

    Loading... Loading…

    Question 95 of 98

    95. P.97 Which of the following does NOT need to be done if there is a major delay on a non-critical path activity?
     
     
     
     

    Question 95 of 98

    Loading... Loading…

    Question 96 of 98

    96. P.98 If the optimistic estimate for a task is 12 days and the pessimistic estimate is 18 days, what is the most likely estimate?
     
     
     
     

    Question 96 of 98

    Loading... Loading…

    Question 97 of 98

    97. P.99 The sponsor of the project you are managing asks you to compress the duration of the project. Which of the following is correct?
     
     
     
     

    Question 97 of 98

    Loading... Loading…

    Question 98 of 98

    98. P.100 The relationships in an activity-on-arrow diagram are:
     
     
     
     

    Question 98 of 98

    Loading... Loading…
    Loading... Loading…

     

    Tag:Exam Questions, PSP, PSP Certificate

    • Share:
    Hany Ismail, MSC, PMP
    Hany Ismail, MSC, PMP

    Hany Ismael is the founder and CEO of Planning Engineer Est. in Egypt. He has started his career back in 2003 as a site engineer, technical office engineer, planning engineer, planning manager, and finally planning department manager where he has been involved in several mega construction projects in Egypt and Saudi Arabia. In 2016, he established his own company in Egypt “Planning Engineer Est.” Hany gained his MSc degree in project management from Liverpool University-UK 2013-2016, PMP certified from PMI-USA 2010, and BSc Civil Engineer Tanta University-Egypt 2003. Hany provided more than 3,500 hours of planning and project management training on his website planningengineer.net, YouTube channel, and offline courses since 2011. He enjoys teaching project management in simple and practical way, and he developed several planning tools, techniques and courses.

    Previous post

    Are you a Professional Engineer?
    October 29, 2016

    Next post

    Equipment Depreciation
    November 5, 2016

    You may also like

    2022-06-28_13-53-15
    Variation Orders and EOT
    29 June, 2022
    img_0142.jpg
    How to perform Cost Control in Construction Projects
    29 September, 2020
    getty_506903004_200013332000928076_348061
    How to change Your Career to a Planning Engineer
    10 December, 2019

      4 Comments

    1. blank
      Nauman
      November 3, 2016
      Log in to Reply

      This Planning Scheduling & Professional 100 questions are of real value. Thanks for sharing the knowledge of Planning Field

      • Hany Ismail, MSC, PMP
        Hany Ismael
        November 5, 2016
        Log in to Reply

        You most welcome 🙂

    2. blank
      Kazeem
      November 7, 2016
      Log in to Reply

      Thanks Ismael. I have benefited a lot from your site.

      I scored 65% for the free PSP Exam. Is this good enough to sit for the real Exam?

      Thanks once again.

    3. blank
      plancoster
      July 30, 2019
      Log in to Reply

      Thanks & Terrific Job ismail, really done great work…people will get benefited too.

    Leave A Reply Cancel reply

    You must be logged in to post a comment.

    Cart

    0

    Planning Courses

    Cost Control for Construction Projects

    Cost Control for Construction Projects

    $299.00
    Power Bi Monitoring and Controlling with P6

    Power Bi Monitoring and Controlling with P6

    $299.00
    Advanced Planning 3 Courses Package

    Advanced Planning 3 Courses Package

    $499.00
    Data Management and Reporting

    Data Management and Reporting

    $199.00
    Primavera Online Basic Course -Arabic

    Primavera Online Basic Course -Arabic

    $99.00
    Professional Planning Engineer (PPE)

    Professional Planning Engineer (PPE)

    $335.00
    Claims Management and (EOT)

    Claims Management and (EOT)

    $175.00
    Primavera Online Basic Course -English

    Primavera Online Basic Course -English

    $99.00

    Follow Us:

    About Us | Contact Us | Terms of Service | Privacy Policy | Refund Policy

    Copyright ©2012- 2018 planningengineer.net | All materials, unless otherwise noted, were developed originally for Planning Engineer Website. In the event that there is still a problem or error with copyrighted material, the break of the copyright is unintentional and noncommercial and the material will be removed immediately upon presented proof.

    • Planning Courses
    • Planning Jobs
    • Planning Blog
    Posting....