Create Critical Activity Indicator in Primavera P6
Using a combination of Global Change and “Indicators” you can graphically show the critical activities in the schedule with an indicator. Follow these steps
1. Create a User Defined Field
2. Set up as a column in a Layout
3. Create and Execute a Global Change
4. Global Change populates the column