Convert P6 WBS to Activity Codes without SDK
New method to convert any primavera P6 WBS to activity codes without using the SDK old method. Using the attached sheet, you can save hours of manual work using this smart technique.
1- Copy the WBS from Oracle Primavera P6
2- Copy the activities along with its WBS and WBS path
Ready to take your skills to the next level? 🚀 Check out our Special Online Courses! 🚀
Gain valuable insights, boost your career, and learn from industry experts.
3- Name your activity codes.
4- Create the activity codes in Primavera P6
5- Export the activities to the spreadsheet.
6- Fill in the activity code values from the smart sheet
7- Import your sheet again to Primavera P6.
1. First Step
You open WBS in Primavera then Copy and Paste it into the attached Excel sheet

Paste it into our Excel sheet in the WBS Sheet

2. Second Step
We need to fill the Second sheet with it’s headings from Primavera

We need to show some columns to fill this sheet as these columns are already in Primavera

This is the layout of Primavera but we need to remove all the WBS in the Schedule

So From Group and Sort Choose Delete then OK

This is how we will copy and paste them into our Excel sheet

These are the Activities from P6 and you need to Delete your first row at the Activities Sheet

If you notice that every WBS is separated by ( . ) then will put every path in a standalone Column
From the Data choose Text to Column to distribute the Path of the activity
All you need to select the WBS Path Column
Click on Next but make sure that the path will not exceed 7 variables due to having some formulas after the 7 Column or you need to add some dummy columns to avoid messing with the Formulas

Choose Other: and type ( . ) to put every number in a column then Next

Choose Finish to the distribution of the Path

This will be the WBS Path Distributed in WBS Path, Column 1, Column 2

3. Third Step
You need to go back to the WBS sheet and remove the Spaces before the Path
Choose Find and Replace then type 2 spaces then Replace All to remove the spaces

Primavera Online Basic Course -English
Online Primavera P6 Course for Engineers & Construction Managers Learn how to use Oracle Primavera P6 to plan, schedule, monitor, and control…
- 5,661 students
- WhatsApp support group
- Certificate

The WBS Without Spaces

If you go to the activities sheet you will find the WBS Level
The WBS level will be filled, and then go to the Activity Codes sheets

This is the Code sheet Filles with #N/A
All you need to see the Labels is to Refresh the sheet

After Refreshing the the file the Row Labels will show up

Activities without any #N/A

Now you need to drag the WBS Code

After Dragging the WBS Code

The Activity Codes have the Activity ID and the whole WBS but you need to do a Refresh to complete the all codes

After refresh

Last Step
The Last step which unfortunately will be done manually in Primavera will be how to add the activity codes.
From Enterprise choose Activity Codes and Click on Modify.

Add new Codes same as these

We will choose the First Code WBS0 and we will type the name and code from the Excel sheet

This will be the Code we will add to this sheet

For the WBS1

For the WBS2 codes

The final step is to import the Codes to Primavera
From the File menu Choose Export Them choose Spreadsheet XLSX

Choose Activities and then Click Next

Choose Export and then Click Next

Choose Modify to choose the exported Columns

From Activity Codes Project Show all the 2 columns WBS0 WBS1 WBS2 to import them back to Primavera

Click finish to open the exported Excel sheet

This is the Exported sheet and our sheet so we are going to VLOOKUP the Activity ID Choose WBS0 for the First Column and repeat this step for WBS1 WBS2

You should make sure that you have no blanks or N/A

Then Copy and paste them as values to remove the VLOOKUP formula then import them back to Primavera
This is how the WBS as activity Code what if you have more than 8 levels or more than 1000 activity

Watch the below video for the exact steps:
Download Resources of this Article
Convert P6 WBS to Activity Codes without SDK 2.17 MB 6398 downloads
Keep growing with Planning Engineer
Learn with a clear path
From Primavera P6 basics to claims, cost control and Power BI. Start with our free courses.
Browse coursesGet help on WhatsApp
Every course comes with a private WhatsApp support group where our team answers your questions.
Join a courseFind planning jobs
68 open planning and project control jobs. Post your resume so employers can find you.
See jobsGet tips by email
Free planning tips, templates and course offers. Unsubscribe any time.
Leave A Reply
You must be logged in to post a comment.










1 Comment
i was not able to find the excel file