What Are the Typical Activities Under the Procurement WBS?
Introduction
In any construction project, procurement plays a critical role in ensuring materials arrive on time, meet specifications, and fit within the project budget. To achieve efficiency and organization, a Procurement Work Breakdown Structure (WBS) is implemented.
This WBS helps in structuring procurement tasks, breaking them into manageable components, and ensuring smooth coordination between suppliers, contractors, and project managers. The procurement WBS typically consists of four or five key activities, depending on whether the material requires fabrication. Additionally, procurement WBS can be structured in two ways:
- Material-Based WBS – where each material has its own WBS with 4 or 5 activities.
- Trade-Based WBS – where materials are grouped under major trade categories like Structural, Architectural, and MEP materials with sub-WBS elements.
Let’s explore these types and the typical activities involved in the procurement of WBS in detail.
Ready to take your skills to the next level? 🚀 Check out our Special Online Courses! 🚀
Gain valuable insights, boost your career, and learn from industry experts.
Types of Procurement WBS
1. Material-Based WBS
- This method is called WBS based on the material (e.g., Reinforcement Steel, Concrete Blocks, HVAC Ducts).
- Each material includes 4 or 5 activities depending on whether fabrication is required.
- Example Activity cycle for Steel Beams (Fabrication Required):
- 1.1 Steel Beams – Material Submittal
- 1.2 Steel Beams – Material Approval
- 1.3 Steel Beams – Purchase Order
- 1.4 Steel Beams – Manufacturing & Fabrication
- 1.5 Steel Beams – Delivery to Site
For materials that don’t need fabrication, the fourth step is skipped, making it a 4-activity WBS.
2. Trade-Based WBS
- Materials are categorized under four main trade categories:
- Structural Materials (Concrete, Steel Reinforcement)
- Architectural Materials (Tiles, Paint, Windows)
- Mechanical Materials (HVAC Ducts, Plumbing Pipes)
- Electrical Materials (Cables, Fixture)
- Instead of naming each material separately, the WBS follows this structure:
- Material Submittal
- Structural
- Architectural
- Mechanical
- Electrical
- Material Approval
- Structural
- Architectural
- Mechanical
- Electrical
- Material PO
- Structural
- Architectural
- Mechanical
- Electrical
- Material Delivery to Site
- Structural
- Architectural
- Mechanical
- Electrical
- Material Submittal
This approach is simpler but might be less detailed compared to Material-Based WBS.
Typical Activities Under Procurement WBS
1. Material Submittal
- The contractor prepares a Material Submittal containing:
- Technical specifications
- Product samples (if required)
- The submittal is sent to the consultant or client for review.
2. Material Approval
- The consultant reviews the Material Submittal against project requirements.
- They may approve, reject, or request revisions.
- Approval delays can affect the project timeline, making this a critical step.
3. Purchase Order (PO)

Primavera Online Basic Course -English
Online Primavera P6 Course for Engineers & Construction Managers Learn how to use Oracle Primavera P6 to plan, schedule, monitor, and control…
- 5,625 students
- WhatsApp support group
- Certificate
- Once materials are approved, the Purchase Order (PO) is issued.
- This includes:
- Material quantity and specifications
- Delivery timeline
- Payment terms
4. Manufacturing and Fabrication (If required)
- If a material needs fabrication, it goes into the manufacturing phase.
- Quality checks are conducted to ensure compliance.
- Delays in fabrication often cause schedule risks.
5. Delivery to Site
- The final step is logistics and transportation.
- Upon delivery, materials undergo inspection and verification before acceptance to get ready for the construction phase.
Material-Based WBS vs. Trade-Based WBS
Feature | Material-Based WBS | Trade-Based WBS |
Naming | Each WBS is named by material | WBS is categorized by trade |
Detail Level | More detailed tracking | Simplified tracking |
Best Use Case | When a project requires precise control per material | When managing procurement at a higher level |
Conclusion
A well-structured procurement WBS ensures smooth material procurement, reduces delays, and improves project efficiency. Whether you choose a Material-Based WBS for more detail or a Trade-Based WBS for simplicity, the key is to have clear tracking and timely execution of each procurement step.
Download the Resources of this Article
What Are the Typical Activities Under the Procurement WBS? 277.41 KB 1400 downloads
Keep growing with Planning Engineer
Learn with a clear path
From Primavera P6 basics to claims, cost control and Power BI. Start with our free courses.
Browse coursesGet help on WhatsApp
Every course comes with a private WhatsApp support group where our team answers your questions.
Join a courseFind planning jobs
110 open planning and project control jobs. Post your resume so employers can find you.
See jobsGet tips by email
Free planning tips, templates and course offers. Unsubscribe any time.
Tag:Materials Procurement, WBS