Step 1
Before you start: complete Open the Schedule Update Tool and Select a P6 Project.
Choose Edit in the Tool
Step 2
Enter the progress in this window
Step 3
Select the data date for the update, then click the Next button
Step 4
This window shows the rules that the tool follows to update. If you do not want some rules to run, you can turn them off, then click the Run Verification button.
Step 5
In this window, review the errors, warnings, and changes for the update. Set the working day if needed.
Step 6
If there are errors, click the Errors button to fix them, or click Exclude all activities with errors. Then click the Next button.
Step 7
Click the Update Project button
Next: Review in P6
Follow Review and Schedule the Updated Project in P6 to refresh (F5) and schedule (F9) the updated project in P6.
Update Project in P6 Database Manually in the Tool
Enter the progress manually in the Schedule Update Tool and update a P6 database project.
Guide 5 of 11 in Updating Tool