Step 1
Before you start: complete Open the Schedule Update Tool and Select a P6 Project.
Choose Excel Sheets, then click the Browse button
Step 2
Open the progress sheet path and open it
Step 3
Select the new data date and time for the project, then click the Next button
Step 4
This window shows the rules that the tool follows to update. If you do not want some rules to run, you can turn them off, then click the Run Verification button.
Step 5
In this window, review the errors, warnings, and changes for the progress sheet. Set the working day if needed.
Step 6
If there are errors, click the Errors button to fix them, or click Exclude all activities with errors. Then click the Next button.
Step 7
Click the Update Project button
Next: Review in P6
Follow Review and Schedule the Updated Project in P6 to refresh (F5) and schedule (F9) the updated project in P6.
Update Project in P6 Database from an Excel Progress Sheet
Update a P6 database project using the progress sheet received from site.