One of our students sent a question in an e-mail wondering about weight calculations in his time schedule. He is in a situation where he has a time schedule that has master activities, those activities are cost-loaded as per the …
‘Schedule % Complete’ in Primavera P6 (represents the planned %) calculates its percentage using the cost resource. But if you wanted to measure the ‘Schedule % Complete’ by the weight of the activities, here we will have to use Excel …