• Home
  • Blog
  • Courses
  • Tools
  • Jobs
  • Forums
Have any question?
(00) 201277767728
[email protected]
RegisterLogin
Planning Engineer Est.
  • Home
  • Blog
  • Courses
  • Tools
  • Jobs
  • Forums
      • Cart

        0

    Project Management

    • Home
    • Blog
    • Project Management
    • Variation Orders and EOT

    Variation Orders and EOT

    • Posted by Hany Ismail, MSC, PMP
    • Categories Project Management
    • Date June 29, 2022
    • Comments 0 comment

    Today I received a very nice question asking about variation orders and how we can deal with variation orders in terms of extension of time.

    so now you received a new variation order adding a new scope for your project now what you should do as a planning engineer?

    first of all, you need to deal with the variation order as a new small project, you need to find the engineering procedures like shop drawing submittals, shop drawing approvals material submittals material, approvals material procurement delivery to the site. Then if you have any authorities approvals and then the installation or the execution of the works.

    Then if there are any dependencies between the new scope of work and the original scope of work. let’s say you received a new variation order asking you Mr contractor we would like to change the flooring from porcelain to marble. okay so in that case you need to find the pattern of the marble, submit the shop drawings for approval, submit the material for approval then procure the marble and deliver it to the site to start the installation.

    okay, why this could involve an extension of time? and what is the case where there is no extension of time?

    usually, if it is issued at the beginning of the project then you have sufficient time to do all your engineering and deliver the material to the site and start the installation so you have no issues at all but if the client issued this variation order to you in a later stage of the project where you already had the approved shop drawings and the approved materials and you need to redo all of these works,  then it might involve an extension of time so in that case or in this scenario it is all about the timing.

    So what do you need to do you? We will do this small project starting from the variation order date you receive and as I said before, procuring the material, approving the shop drawings, delivering the material, starting the installation, and then you will import this small project into your original baseline and link the successor and predecessor activities and you will see if the completion date of the project was impacted it means moved, then you have to claim for an extension of time if your project completion date was not impacted it means there are some floats you can use them and you are not entitled to an extension of time.

    So the variation order you need to consider the timing because usually when the variation order is issued at the beginning of the project there is no issue at all, but the most common cause is that during the execution when everyone is busy doing the construction and so on the client start firing variation orders and this is a most critical one because you need to study it immediately and advise the client, Mr. Client, if you insist on this variation order it will cost you this amount of money and it will cost you an additional amount of time.

    Watch the Article Video:

    Tag:EOT, Extension of Time, Variation Orders

    • Share:
    Hany Ismail, MSC, PMP
    Hany Ismail, MSC, PMP

    Hany Ismael is the founder and CEO of Planning Engineer Est. in Egypt. He has started his career back in 2003 as a site engineer, technical office engineer, planning engineer, planning manager, and finally planning department manager where he has been involved in several mega construction projects in Egypt and Saudi Arabia. In 2016, he established his own company in Egypt “Planning Engineer Est.” Hany gained his MSc degree in project management from Liverpool University-UK 2013-2016, PMP certified from PMI-USA 2010, and BSc Civil Engineer Tanta University-Egypt 2003. Hany provided more than 3,500 hours of planning and project management training on his website planningengineer.net, YouTube channel, and offline courses since 2011. He enjoys teaching project management in simple and practical way, and he developed several planning tools, techniques and courses.

    Previous post

    Sample Weekly and Monthly Reports
    June 29, 2022

    Next post

    Primavera P6 Excel Import/Export Require Microsoft Access [Solved]
    June 29, 2022

    You may also like

    img_0142.jpg
    How to perform Cost Control in Construction Projects
    29 September, 2020
    getty_506903004_200013332000928076_348061
    How to change Your Career to a Planning Engineer
    10 December, 2019
    Claim Specialist
    Difference between Claim Specialist and Delay Analyst
    3 March, 2019

    Leave A Reply Cancel reply

    You must be logged in to post a comment.

    Cart

    0

    Planning Courses

    Cost Control for Construction Projects

    Cost Control for Construction Projects

    $299.00
    Power Bi Monitoring and Controlling with P6

    Power Bi Monitoring and Controlling with P6

    $299.00
    Advanced Planning 3 Courses Package

    Advanced Planning 3 Courses Package

    $499.00
    Data Management and Reporting

    Data Management and Reporting

    $199.00
    Primavera Online Basic Course -Arabic

    Primavera Online Basic Course -Arabic

    $99.00
    Professional Planning Engineer (PPE)

    Professional Planning Engineer (PPE)

    $335.00
    Claims Management and (EOT)

    Claims Management and (EOT)

    $175.00
    Primavera Online Basic Course -English

    Primavera Online Basic Course -English

    $99.00

    Follow Us:

    About Us | Contact Us | Terms of Service | Privacy Policy | Refund Policy

    Copyright ©2012- 2022 planningengineer.net | All materials, unless otherwise noted, were developed originally for Planning Engineer Website. In the event that there is still a problem or error with copyrighted material, the break of the copyright is unintentional and noncommercial and the material will be removed immediately upon presented proof.

    • Planning Courses
    • Planning Jobs
    • Planning Blog

    Login with your site account

    Lost your password?

    Not a member yet? Register now

    Register a new account

    Are you a member? Login now