Project Management Plan from Planning Engineer Point of View
3- Manpower Histogram
to create Manpower histogram we need to create an excel sheet similar to the cost loading but we calculate the manpower instead of the budget cost (Resource Loading) as per below example:
after the completion of the resource loading sheet we will upload the primavera with the manpower budgeted units for every activity and this will create the manpower histogram (see sample below) :
Tag:activity list, Bill of Quantities, Cash Flow, cost loading, design drawings, detailed time schedule, featured, Manpower Histogram, Materials Tracking Log, planning engineers, Primavera, Project contractual milestones, project management plan, Shop Drawings tracking log, specifications, Work Break Down Structure
Leave A Reply
You must be logged in to post a comment.
10 Comments
this very good
Thanks Engineer Hassan
very good I wish to joining this group to learn more I have basic.
Really this are usefull.
Fantastic template to maintain your project 🙂
good alot
Really this are useful tips.
Thanks Engineer
appreciated your kind efforts