• Home
  • Blog
  • Courses
  • Tools
  • Jobs
  • Forums
Have any question?
(00) 201277767728
[email protected]
RegisterLogin

Login with your site account

Lost your password?

Not a member yet? Register now

Register a new account

Are you a member? Login now

Planning Engineer Est.
  • Home
  • Blog
  • Courses
  • Tools
  • Jobs
  • Forums
      • Cart

        0

    Project Management

    • Home
    • Blog
    • Project Management
    • Methods to estimate task and activity duration

    Methods to estimate task and activity duration

    • Posted by Hany Ismail, MSC, PMP
    • Categories Project Management
    • Date November 18, 2013
    • Comments 2 comments

    “The duration of a project is the elapsed time in business working days, not including weekends, holidays, or other non-work days. (Wysocki 2012)


    The duration task estimation is a challenge target to the project team. It does not has neither fixed rules nor clear assumptions to follow, it is related to task resources allocation, and could vary from person to another and from project to another. (Wysocki 2012)

    (Wysocki 2012) identified six methods to estimate the project duration as per the following:

    1-   Similarity to other activities

    This method is applicable when we have two similar projects, one finished and another ongoing. In such case, we can use the finished project actual tasks duration along with lessons learned to estimate the new project duration. This method is rarely used in construction projects; it is very hard to find two typical projects on construction field.

    2-   Historical data

    This is a common method of estimating tasks duration on construction projects, we recall the actual productivity rates from completed projects to estimate a new project tasks duration. We use this method to estimate the traditional activities such as masonry works, plaster works, painting, flooring … etc.

    3-   Expert advice
    whenever we have a new task never executed before, or require a special arrangement, we usually refer to an expert to help us estimating the duration. In my current project, we have an auditorium hall where the walls and the celling are covered with wood panels in different angles shapes, the installation method statement of the wood and the hanging system was not clear to the planning team. Therefore, we called the wood subcontractor in the planning process to discuss with him the fabrication, hanging system, and wood installation method statement and the forecast productivity rates. In result, we accurately estimated the task duration.

    4-   Delphi technique

    This method is used when the expert advice is not available by asking a group of participation who are involved on the task about their opinion of task duration. Then tabulate the results and present to the group in a histogram labeled First Pass. We then identify the highest and lowest results and ask the group members who wrote these values to explain their opinion to all group members. Then we ask the group members to write their opinion again to present the Second Pass histogram. Again, we do the same as we did in the First Pass. Finally, we take the average results of the Third Pass as the group’s estimate.

    5-   Three-point technique

    “Task duration is a random variable. If it were possible to repeat the task several times under identical circumstances, duration times would vary.” (Wysocki 2012)

    This is the best way of estimating a task duration when we use it with a historical data. We use this method as a planning team in the critical activities when we have a historical data from more than a project for the same activity.

    I would define the duration types as per the following:

    Optimistic (O): Best-case scenario.

    Pessimistic (P): Worst-case scenario.

    Most likely (M): Usual scenario.

    The famous formula of estimating the task duration is (O + 4M + P) / 6 .

    6-   Wide-band Delphi technique

    This method is a combination of Delphi Technique and Three-Point Technique. Instead of asking the group members to write one number for the expected task duration, they need to guess three numbers (Optimistic, Pessimistic and Most likely). In addition, the histogram calculation takes the average as per Three-Point formula.


    Although, (Wysocki 2012) defined six methods of tasks estimation, but I have another case where it cannot fit to any of them. Resource driving tasks most probably not happened before to refer to Similarity to other activities. Are unique, therefore the Historical data is not useful. Have a certain way of calculating the duration; therefore, Expert advice, Delphi technique, Three-point technique and Wide-band Delphi technique are not applicable. This type of tasks depend purely on the productivity rate of the resources.

    Example: In my current project, the only way to erect the mega roof steel and glass panels is by using the available tower cranes. To estimate the duration required to finish this task we rely on the tower crane productivity, nothing else.

    Task duration = (Panels Quantity) / (Tower crane productivity per day * number of tower cranes)


    Reference:

    WYSOCKI, R.K., 2012. Effective project management. 6th edn. Indianapolis, IN: Wiley.


     

    Download Now our new mobile application for construction productivities from Google Play and Apple Store:

    blank

    Tag:activity, Activity Duration, Delphi technique, duration of a project, elapsed time, Estimate, Estimate Activity Duration, estimate task duration, Expert advice, Historical data, project duration, Similarity to other activities, task, task duration, Three-point technique, Wide-band Delphi technique, WYSOCKI

    • Share:
    Hany Ismail, MSC, PMP
    Hany Ismail, MSC, PMP

    Hany Ismael is the founder and CEO of Planning Engineer Est. in Egypt. He has started his career back in 2003 as a site engineer, technical office engineer, planning engineer, planning manager, and finally planning department manager where he has been involved in several mega construction projects in Egypt and Saudi Arabia. In 2016, he established his own company in Egypt “Planning Engineer Est.” Hany gained his MSc degree in project management from Liverpool University-UK 2013-2016, PMP certified from PMI-USA 2010, and BSc Civil Engineer Tanta University-Egypt 2003. Hany provided more than 3,500 hours of planning and project management training on his website planningengineer.net, YouTube channel, and offline courses since 2011. He enjoys teaching project management in simple and practical way, and he developed several planning tools, techniques and courses.

    Previous post

    How to force your manager to listen to you?
    November 18, 2013

    Next post

    Network Diagram Honor Board
    November 28, 2013

    You may also like

    img_0142.jpg
    How to perform Cost Control in Construction Projects
    29 September, 2020
    getty_506903004_200013332000928076_348061
    How to change Your Career to a Planning Engineer
    10 December, 2019
    Claim Specialist
    Difference between Claim Specialist and Delay Analyst
    3 March, 2019

      2 Comments

    1. blank
      Joaquin Miclat
      November 3, 2020
      Log in to Reply

      Hi Hani,

      I’m planning a new oil & gas project but I don’t have any reference in assigning duration to each activity, civil, mechanical, etc. Could you advise what reference should I refer to?

      Jack Miclat

      • Hany Ismail, MSC, PMP
        Hany Ismail, MSC, PMP
        November 4, 2020
        Log in to Reply

        Usually I consultant the project manger and construction manager for the activities I cannot estimate it’s duration. Furthermore, for activities in special categories, we might ask the specialist of the category to advise you about the most likely duration.

    Leave A Reply Cancel reply

    You must be logged in to post a comment.

    Cart

    0

    Planning Courses

    Cost Control for Construction Projects

    Cost Control for Construction Projects

    $299.00
    Power Bi Monitoring and Controlling with P6

    Power Bi Monitoring and Controlling with P6

    $299.00
    Advanced Planning 3 Courses Package

    Advanced Planning 3 Courses Package

    $499.00
    Data Management and Reporting

    Data Management and Reporting

    $199.00
    Primavera Online Basic Course -Arabic

    Primavera Online Basic Course -Arabic

    $99.00
    Professional Planning Engineer (PPE)

    Professional Planning Engineer (PPE)

    $335.00
    Claims Management and (EOT)

    Claims Management and (EOT)

    $175.00
    Primavera Online Basic Course -English

    Primavera Online Basic Course -English

    $99.00

    Follow Us:

    About Us | Contact Us | Terms of Service | Privacy Policy | Refund Policy

    Copyright ©2012- 2018 planningengineer.net | All materials, unless otherwise noted, were developed originally for Planning Engineer Website. In the event that there is still a problem or error with copyrighted material, the break of the copyright is unintentional and noncommercial and the material will be removed immediately upon presented proof.

    • Planning Courses
    • Planning Jobs
    • Planning Blog
    Posting....