Shrief El Gendy replied to the topic Primavera is not automatically calculating labor hours in the forum Professional Planning Engineer (PPE) Support Forums 1 month, 1 week ago
Check out the steps in this article. If you still have the same problem after reading and applying the methods in the article, please reply.
Actual cost not calculated automatically – Primavera P6 (Solved)
-
Shrief El Gendy replied to the topic database issue in the forum Power Bi Monitoring and Controlling with P6 Support Forums 1 month, 1 week ago
I got you, that’s because you’re searching for the activity name with a generic name.
The activity name that has the ID PE-260-ED1680 is called “Protection System Works | Approval”, so in order to get its relevant actual dates, you have to search with its full name, and this name shouldn’t be duplicated in another activity.
Your case here is…Read more
-
Shrief El Gendy replied to the topic Production rate software in the forum كورس مهندس تخطيط ومتابعة مستوى متوسط – منتدى الدعم 1 month, 1 week ago
ممكن تاخد سكرين شوت من المشكلة أو الإيرور اللي بيظهر لك وترفع الصورة هنا؟
-
Shrief El Gendy replied to the topic database issue in the forum Power Bi Monitoring and Controlling with P6 Support Forums 1 month, 1 week ago
Hi Bilal, how are you? I hope you’re having a great day!
I downloaded your files and connected the database to the power bi file, refreshed the queries, and went to data view and found that all the actuals data are included in the data table already.
You maybe find it as blanks (activities that have no actuals yet), just scroll down and you’ll…Read more
-
Shrief El Gendy replied to the topic actual % cost in the forum Power Bi Monitoring and Controlling with P6 Support Forums 1 month, 2 weeks ago
If you want to multiply the actual cost by the actual % cost and then compare it to the planned total cost to get the variance, you have to create a new measure that calculates ( Actual cost * Actual Cost % ) and then use it in the comparison.
To do so, click on the “Table Tools” menu, then choose Quick Measure.
You can also add a quick…Read more
-
Shrief El Gendy replied to the topic summarizing activity cost with another table in the forum Power Bi Monitoring and Controlling with P6 Support Forums 1 month, 2 weeks ago
I didn’t understand your question clearly but I’ll give you my opinion,
When you click on the checkbox of any data column from your data side section, it will insert a new table containing that column without the need of inserting a table visual then adding the data to it. (Make sure you’re not selecting any visuals in your report before clicking…Read more -
Shrief El Gendy replied to the topic Schedule and Performance percent complete progress showing zero progress in the forum Basic Planning Course Support Forums 1 month, 3 weeks ago
Make sure also to verify that you already run (schedule) your project at the appropriate data date that you want to calculate the progress.
-
Shrief El Gendy replied to the topic Schedule and Performance percent complete progress showing zero progress in the forum Basic Planning Course Support Forums 1 month, 3 weeks ago
Are your activities cost-loaded?
-
Shrief El Gendy replied to the topic Activities breakdown from level 3 to level 4 in the forum Construction Project Planning Intermediate Level with P6 Support Forums 1 month, 3 weeks ago
For the last question, Ideally, the L4 schedule should be a more detailed breakdown of the L3 schedule. It should contain activities that are directly related to and support the L3 activities.
This hierarchical structure allows for a better view of the work while still linking back to the higher-level objectives of the project.
So, both L4 and…Read more
-
Shrief El Gendy replied to the topic Activities breakdown from level 3 to level 4 in the forum Construction Project Planning Intermediate Level with P6 Support Forums 1 month, 3 weeks ago
Regarding the second concern that the schedule has a lot of negative floats, I think you should have a meeting with the planning engineer of the contractor and ask him to specify the reasons for that negative float for each activity.
If his reasons are logical and he has an action plan to get the project on track, so you are free to accept the…Read more
-
Shrief El Gendy replied to the topic Activities breakdown from level 3 to level 4 in the forum Construction Project Planning Intermediate Level with P6 Support Forums 1 month, 3 weeks ago
Hi Dario,
Regarding your first concern,
I agree with you that you have to control and make sure that the weekly update percentages represent the actual work on site. The easy solution for this problem is to have site audits.Each week pick some activities and check their status by yourself to know if the percentage that the contractor submits to…Read more
-
Shrief El Gendy replied to the topic Using power query in cases with stages and zones in the forum Construction Project Planning Intermediate Level with P6 Support Forums 1 month, 3 weeks ago
Hi Engineer Waseem,
I think both courses (Intermediate and PPE) are teaching concepts, not steps. So, if you understood the concept of using power query in the PPE course, then you can apply it to any project.
To answer your question, please tell me which lesson of the PPE course you think can’t be applied in the intermediate. Also if you…Read more -
Shrief El Gendy replied to the topic How to convert Hard-copy schedule to XER? in the forum Professional Planning Engineer (PPE) Support Forums 1 month, 4 weeks ago
My answer to this question was:
I. Ordinary Solutions:
1. Export the XER file to PDF and compare the following between the PDF and the printed version:
• Pages number
• Rows at the last page (indicates if any rows are missing)
• WBS order and names
• WBS total values
• Milestones dates
• Layout canvas size, logo size, title size, and colors…Read more -
Shrief El Gendy started the topic How to convert Hard-copy schedule to XER? in the forum Professional Planning Engineer (PPE) Support Forums 1 month, 4 weeks ago
One student sent this question by email, I’ll answer in the first reply.
Question:
I’m in a situation where I have a time schedule as a hard copy only. I have printed time schedule from Primavera and I want to create a soft copy for the time schedule. Could you help?
-
Shrief El Gendy replied to the topic Negotiating Analysis method with the consultant in the forum Claims Management and (EOT) Support Forums 1 month, 4 weeks ago
My reply to his email was as follows:
I understand that you have encountered some resistance from a consultant who insists on using only the Time Impact Analysis (TIA) method.
I will provide you with a detailed explanation of the main reasons you can use to help the consultant understand the benefits of combining the “Impacted as Planned” (IAP)…Read more
-
Shrief El Gendy started the topic Negotiating Analysis method with the consultant in the forum Claims Management and (EOT) Support Forums 1 month, 4 weeks ago
We received this question in an email, and we will answer it in the first reply.
would ask about Delay Analysis Techniques ( week 4 ):-
What Are the Main reasons that I can Explain to a consultant to understand Using this method he refused to mix two methods and forced me to use only (TIA) which is the correct one.
-
Shrief El Gendy replied to the topic What should we do, that our project should complete within Budget? in the forum Basic Planning Course Support Forums 1 month, 4 weeks ago
Our answer:
- Completing your project within budget has unlimited factors that affects the budget, but we can help you and provide a list of the most important terms that directly affect the budget.
1- Accurate cost estimation: Estimating the cost from the beginning can help a lot.
2- Create a realistic budget: Consider unexpected costs and… - Completing your project within budget has unlimited factors that affects the budget, but we can help you and provide a list of the most important terms that directly affect the budget.
-
Shrief El Gendy started the topic What should we do, that our project should complete within Budget? in the forum Basic Planning Course Support Forums 1 month, 4 weeks ago
One of our students asked this question via mail, we will answer it in the first reply.
Question:
What should we do, that our project should complete within Budget…?
-
Shrief El Gendy replied to the topic What is Site Allocation? in the forum Basic Planning Course Support Forums 1 month, 4 weeks ago
Our Answer:
Site allocation is one of the very effective and important things that should be considered while starting a new project. Site allocation is how to use your site area effectively to get the highest productivity. Selecting the specific locations of the storages and storing specific materials is site allocation. Creating movement Plan…
-
Shrief El Gendy started the topic What is Site Allocation? in the forum Basic Planning Course Support Forums 1 month, 4 weeks ago
One of our students asked this question via mail, we will answer it in the first reply.
Question:
What is Site Allocation…?