Dario Natingue replied to the topic Activities breakdown from level 3 to level 4 in the forum Construction Project Planning Intermediate Level with P6 Support Forums 1 month, 3 weeks ago
Hi Eng. Gendy,
First of all I want to thank You all (the TEAM) for creating this forum!
Today You have helped me and I am very sure that You will help someone else in the future.Secondly I would like to let You know that I am happy with all Your responses and even happier because I also had the same thinking, meaning that I was not lost in my…Read more
-
Dario Natingue started the topic Activities breakdown from level 3 to level 4 in the forum Construction Project Planning Intermediate Level with P6 Support Forums 1 month, 3 weeks ago
Hi all,
I am a SITE planner at a client side on my project.
The project has been started and running without a project control department on both sides (Client and Contractor). The stakeholders end up deciding to have planners to control the project, that is when I was hired 2 months ago. My concern is that since I have joined, I have a filling…Read more