Hany Ismail, MSC, PMP replied to the topic this course extension in the forum Power Bi Monitoring and Controlling with P6 Support Forums 1 week, 3 days ago
Dear Engineer Bilal, I will consider doing this.
-
Hany Ismail, MSC, PMP replied to the topic I can not download file in the forum Claims Management and (EOT) Support Forums 3 weeks, 6 days ago
Hello Spromkete,
I am not sure why you cannot download it. Have you tried saving the link as?
I am attaching the lesson files for your reference here in this reply.
-
Hany Ismail, MSC, PMP replied to the topic Additional course in the forum Power Bi Monitoring and Controlling with P6 Support Forums 3 weeks, 6 days ago
Good to know it is now working 🙂
-
Hany Ismail, MSC, PMP replied to the topic استفسار بخصوص توزيع الانشطة علي كل دور in the forum كورس مهندس تخطيط ومتابعة مستوى متوسط – منتدى الدعم 3 weeks, 6 days ago
وعليكم السلام ورحمة الله وبركاته
مفيش حاجه لازم … الموضوع كله يتوقف على متطلبات التخطيط فى مشروعك.
على سبيل المثال اذا كنت هتابع كل عماره لوحدها يبقى لازم توزع الكميات على كل عماره أما لو هتابع كل مجموعة عمارات مع بعض يبقى ممكن تقسمهم مناطق و تقسم الكميات طبقا لكل منطقه و هكذا.. -
Hany Ismail, MSC, PMP replied to the topic Updating progress of the project in the forum Basic Planning Course Support Forums 3 weeks, 6 days ago
Hello Planning Engineers,
Sure you can use Excel to update your schedule Actual %, Actual Start, and Actual Finish. I am using this method because it is much more easy. I have created a complete tutorial for doing this starting with the Excel template you need to use to get your update until you import the update from Excel to P6. Please check…Read more
-
Hany Ismail, MSC, PMP replied to the topic open new project in P6 in the forum Basic Planning Course Support Forums 1 month, 1 week ago
Hello Engineer Khaled. Just click on the activities tap as per the attached screenshot.
-
Hany Ismail, MSC, PMP replied to the topic سؤال فى الابديت in the forum كورس مهندس تخطيط ومتابعة مستوى متوسط – منتدى الدعم 1 month, 2 weeks ago
وعليكم السلام ورحمة الله وبركاته.
يمكن تغيير بعض العلاقات بين الانشطه اثناء تحديث البرنامج الزمنى مع عمل جدول بالتغيرات التى تمت وارفاقه بالتقرير. عادة ما يكون هذا مسموح فى حدود معينه لتغيير بعض العلاقات البسيطه. ولكن اذا كانت هناك تغيررات كبيره فى سياق سير العمل يجب عمل برنامج معدل ليعكس الاعمال المتوقعه و تواريخها.
أحيانا بنقدم جدول معدل فقط ل…Read more -
Hany Ismail, MSC, PMP replied to the topic Database for Multiples project in the forum Power Bi Monitoring and Controlling with P6 Support Forums 1 month, 2 weeks ago
Dear Engineer Bilal,
Thanks for your question. Yes of course you can add more than one project in the database. It is the main purpose of using Power Bi actually. You can update each project and use our Excel Macro to do so then paste the results to the database and start adding a new project and so on. The data should not be overlapping if you…Read more
-
Hany Ismail, MSC, PMP replied to the topic Activities delayed due to predecessor or successor in the forum Basic Planning Course Support Forums 1 month, 3 weeks ago
Dear Engineer Sheraz Ahmad,
Please find my reply to your questions as follows:
1 – Activities delayed due to predecessor or successor delay. This is Normal, you need to adjust the relationships or durations in your baseline to fulfill the expected dates.
2 – Activities delayed due to resource leveling. If you are using the P6 automated res…Read more -
Hany Ismail, MSC, PMP replied to the topic Engineering man hours in the forum Professional Planning Engineer (PPE) Support Forums 1 month, 3 weeks ago
Dear Engineer Mohammed,
We have prepared the attached article for your question.
-
Hany Ismail, MSC, PMP replied to the topic Schedule and Performance percent complete progress showing zero progress in the forum Basic Planning Course Support Forums 1 month, 3 weeks ago
Please use the following method to upload your XER file: https://planningengineer.net/forums/topic/how-to-attach-xer-or-power-bi-file/
-
Hany Ismail, MSC, PMP replied to the topic Delay Event fragnet in the forum Claims Management and (EOT) Support Forums 1 month, 3 weeks ago
Hello Engineer Mohammad Bilal,
Thanks for this interesting question.
First of all, unless it is clearly mentioned in the contract that the contractor should use this specific delay analysis method, you can negotiate with the client to use the relevant method that best fits your project and your situation.
As per AACE Retrospective analyses:…Read more
-
Hany Ismail, MSC, PMP replied to the topic the project did not equal the total activity Multiply in the percentage of the week in the forum Data Management and Reporting Support Forums 1 month, 4 weeks ago
My answer was:
Dear Engineer Sameh Elsewedy,
I think you need to increase the decimals on your percentage. For example, use 30.12% instead of 30.1%
You are welcome to share your file so I can help you further.
-
Hany Ismail, MSC, PMP started the topic the project did not equal the total activity Multiply in the percentage of the week in the forum Data Management and Reporting Support Forums 1 month, 4 weeks ago
I received this email:
When making the first report, I found the value of the project did not equal the total activity Multipli in the percentage of the week. Why?
And at the rate of the week in the value of the activity?
Why were many of the values changed to match the result of the week’s percentages?
Summary of the question
The project value…Read more -
Hany Ismail, MSC, PMP replied to the topic inconsistency of the project value in both files in the forum Data Management and Reporting Support Forums 1 month, 4 weeks ago
My reply was:
Dear Engineer Sameh Elsewedy,
You are missing these two activities in your weekly distribution:
St-S-EX-0-3-2a
St-S-EX-0-3-2bPlease see the attached file with my checks.
-
Hany Ismail, MSC, PMP started the topic inconsistency of the project value in both files in the forum Data Management and Reporting Support Forums 1 month, 4 weeks ago
I received this question by email:
Dear Engineer hany,
These are the files attached to the course
the first ProjectDatabaseR0
The second ProjectDatabaseR1
The problem is the inconsistency of the project value in both files -
Hany Ismail, MSC, PMP replied to the topic Planned Values not working in the forum Power Bi Monitoring and Controlling with P6 Support Forums 1 month, 4 weeks ago
My reply was
Dear Engineer makki bilal,
The problem was in your model relationships. The date relationship was not active (dotted). See the below screenshot:
I removed the relationship between the activities (activity ID) and P_values (activity id) and E_values (activity id). To make the dates relationships active. Double-click the dotted…Read more
-
Hany Ismail, MSC, PMP started the topic Planned Values not working in the forum Power Bi Monitoring and Controlling with P6 Support Forums 1 month, 4 weeks ago
I received this question
Dear Mr.Hanry
Am making dashboard as following your steps in video , but there is a problem that in my excel file earned value I have consider till 23 Apr, but in dashboard in power bi its showing ilsome amount of earned value in oct-23 , how to fix this issue ? -
Hany Ismail, MSC, PMP replied to the topic Interview Questions-Answer about Costs in the forum Cost Control for Construction Projects Support Forums 1 month, 4 weeks ago
My answer was:
Dear Engineer HABIBULLAH NAWAZ,
Q-1: The difference between a prime cost sum and a provisional sum…?
A-1: Assume you’re in the tender process and preparing your financial proposal or estimating the cost of the project, there are always some items (equipment, material,…) that you are not sure about their cost. You also may find…Read more -
Hany Ismail, MSC, PMP started the topic Interview Questions-Answer about Costs in the forum Cost Control for Construction Projects Support Forums 1 month, 4 weeks ago
I received this question :
Greetings,
Respected Sir.Hany Ismail,
I hope you are having a wonderful day, I am Engr Habib Ullah,I am your student, and I really appreciate what you are doing by assisting learners who are new to engineering and want to learn more about their field.
Your method of teaching is very gentle and makes it simple to…Read more - Load More