Import progress updates with actual dates to primavera p6
This method will help you to send your site team an excel sheet extracted from the Oracle Primavera Baseline schedule showing the Planned %, planned start, and planned finish to update the Actual start, Actual finish, and the actual % completed.
By doing this, you are giving your site team an idea about the % they should achieve so far and reducing your efforts to import this sheet directly to your updated schedule saving lots of working hours.
Watch the lesson video:
Download the Resources of this Article
Convert from Primavera to Excel 23.97 KB 29268 downloads
Keep growing with Planning Engineer
Learn with a clear path
From Primavera P6 basics to claims, cost control and Power BI. Start with our free courses.
Browse coursesGet help on WhatsApp
Every course comes with a private WhatsApp support group where our team answers your questions.
Join a courseFind planning jobs
25 open planning and project control jobs. Post your resume so employers can find you.
See jobsGet tips by email
Free planning tips, templates and course offers. Unsubscribe any time.
Leave A Reply
You must be logged in to post a comment.









2 Comments
I need the excel sheet to send to (site team an excel sheet extracted I from the Oracle Primavera Baseline schedule showing the Planned %, planned start, and planned finish to update the Actual start, Actual finish, and the actual % completed.)
With same colors for each rows
Convert from Primavera to Excel i need this file ! can i get for free