    Planning Using Primavera

    • Home
    • Blog
    • Planning Using Primavera
    • how to create work breakdown structure WBS using standard Division of work

    how to create work breakdown structure WBS using standard Division of work

    • Posted by Hany Ismail, MSC, PMP
    • Categories Planning Using Primavera
    • Date February 14, 2013
    • Comments 3 comments

    Division 8 – Doors and Windows

    Steel Doors and Frames

    Steel Doors and Frames (full synopsis)

    Steel Door Frames (full synopsis)

    Bullet-Resistant Steel Doors and Frames

    Aluminum Doors and Frames (full synopsis)

    Aluminum Door Frames

    Stainless Steel Doors and Frames

    ICU/CCU Sliding Doors

    Flush Wood Doors (full synopsis)

    Stile and Rail Wood Doors (full synopsis)

    Fiberglass Doors and Frames

    Sliding Glass Doors (full synopsis)

    Lift-Sliding and Sliding-Folding Glass Doors

    Access Doors and Panels (full synopsis)

    Overhead Coiling Doors (full synopsis)

    Overhead Coiling Grilles (full synopsis)

    Overhead Coiling Wood Counter Doors

    Records Vault Doors

    Accordion Folding Doors (full synopsis)

    Accordion Folding Doors

    Folding Fire Doors

    Overhead Doors (full synopsis)

    Overhead Doors

    Double-Acting Traffic Doors

    Blast Resistant Steel Door Systems

    Watertight Doors and Flood Barriers

    Hurricane Resistant Doors

    Metal-Framed Storefronts (full synopsis)

    All-Glass Entrances and Storefronts

    Automatic Entrance Doors (full synopsis)

    Automatic Swinging Doors

    Automatic Sliding Doors

    Automatic Folding Doors

    Revolving Entrance Doors (full synopsis)

    Balanced Entrance Doors

    Between Glass Venetian Blinds

    Steel Windows (full synopsis)

    Aluminum Windows (full synopsis)

    Wood Windows (full synopsis)

    Tubular Plastic Windows (full synopsis)

    Vinyl Interior Windows

    Custom Storm Windows

    Security and Detention Windows (full synopsis)

    Hurricane Resistant Windows

    Unit Skylights (full synopsis)

    Tubular Skylights (full synopsis)

    Metal-Framed Skylights (full synopsis)

    Door Hardware (full synopsis)

    Architectural Hinges

    Continuous Geared Hinges

    Door Locks

    Door Trim

    Sliding and Folding Door Hardware

    Sliding Door Hardware

    Thresholds and Weatherstripping

    Electrical Locking Control

    Low-Energy Door Operators

    Fire Door Operators

    Window Hardware

    Glazing (full synopsis)

    Mirrors (full synopsis)

    Cellular Plastic Glazing

    Safety and Security Glazing Film (full synopsis)

    Solar Control Glazing Film

    Metal-Framed Curtain Wall (full synopsis)

    Translucent Wall and Roof Assemblies (full synopsis)

    Structural Glass Curtain Wall (full synopsis)

     


    Division 9 – Finishes specification sections

    Non-Loadbearing Metal Framing

    Metal Lath

    Gypsum Plaster

    Gypsum Veneer Plaster

    Portland Cement Plaster

    Exposed Aggregate Pool Finish

    Glass Fiber Reinforced Gypsum Fabrications

    Gypsum Board Assemblies

    Clay Tile and Stair Treads

    Tile Setting Materials and Methods

    Tile Setting Materials and Accessories

    Tile Setting Materials and Accessories

    Slate Tile

    Portland Cement Terrazzo

    Plastic Matrix Terrazzo

    Terrazzo Tile

    Suspended Acoustical Ceilings

    Adhesive Applied Acoustic Ceilings

    Fabric-Faced Acoustical Ceilings

    Linear Metal Ceiling

    Integrated Ceiling

    Luminous Ceiling

    Resilient Athletic Flooring

    Stone Flooring

    Brick Flooring

    Hardwood Flooring – Adhesive Applied

    Hardwood Flooring – Nailed

    Engineered Wood Plank Flooring

    Bamboo Plank Flooring

    Resilient Flooring

    Static Control Flooring

    Fluid-Applied Flooring

    Resilient Urethane Flooring

    Concrete Floor Coatings

    Carpet

    Carpet Tile

    Wall Covering

    Wall Fabrics

    Prefinished Panels

    Acoustical Wall Systems

    Acoustical Panels

    Metal-Faced Acoustical Panels

    Acoustical Panels, Baffles, Diffusers, and Reflectors

    Paints and Coatings

    Paints and Coatings

    Paints and Coatings

    Paints and Coatings

    Paints and Coatings

    Paints and Coatings

    Paints and Coatings

    Exterior Paints and Stains

    Interior Paints and Stains

    Stains and Transparent Finishes

    Stains and Transparent Finishes

    High-Performance Coatings

    High-Performance Coatings

    High-Performance Coatings

    Floor Coatings

    Aggregate Wall Surfacing

    Cementitious Coating

     


    Division 10 – Specialties specification sections

    Visual Display Boards

    Tackable Wall Systems

    Metal Toilet Compartments

    Plastic Laminate Toilet Compartments

    Plastic Toilet Compartments

    Cubicle Curtains

    Wall Louvers

    Rooftop Equipment Screens

    Wall and Corner Guards

    Handrails

    Wall Guards

    Corner Guards

    High Impact Wall Covering

    Access Flooring

    Architectural Bird Control

    Manufactured Fireplaces

    Gas-Burning Fireplaces and Stoves

    Prefabricated Steeple and Cupola

    Flagpoles

    Interior Signage

    Plastic Signs

    Door and Room Signs

    Lockers

    Polyethylene Lockers

    Wire Mesh Lockers

    Fire Extinguishers, Cabinets and Accessories

    Protective Covers

    Awnings

    Mail Chutes

    Mail Boxes

    Wire Mesh Partitions

    Wire Mesh Partitions and Railings

    Folding Gates

    Demountable Gypsum Board Partitions

    Operable Panel Partitions

    Accordion Folding Partitions

    Metal Storage Shelving

    Wire Storage Shelving

    Wall Mounted Standards and Shelving

    Movable Shelving System

    Exterior Sun Control Devices

    Rolling Shutters

    Exterior Shutters

    Coiling Insect Screens

    Toilet, Bath, and Laundry Accessories

    Toilet Accessories

    Electric Hand Dryers

     


    Division 11 – Equipment specification sections

    Window Washing Equipment

    Building Maintenance Access Equipment

    Projection Screens

    Parking Control Equipment

    Parking Gates and Operators

    Dock Levelers

    Dock Seals and Shelters

    Dock Bumpers

    Waste Compactors

    Food Service Equipment

    Custom Fabricated Food Service Equipment

    Hood and Ventilation Equipment

    Residential Equipment

    Revolving Darkroom Doors

    Swimsuit Water Extractors

    Gymnasium Equipment

    Laboratory Equipment

    Laboratory Fume Hoods

    Laboratory Fume Hoods

    Self-Contained Filtered Laboratory Enclosures

    Biological Safety Cabinets

    Laboratory Glassware Washer/Dryers

     


    Division 12 – Furnishings specification sections

    Metal Casework

    Residential Casework

    Foot Grilles, Mats, and Frames

    Floor Mats

    Horizontal Louver Blinds

    Drapery Track

    Window Shade Systems

    Mailroom Furniture

    Fixed Theater Seating

    Telescoping Bleachers

     


    Division 13 – Special Construction 

    Saunas

    Steam Rooms

    Cold Storage Rooms

    Prefabricated Rooms

    Bullet-Resistant Fiberglass Panels

    X-Ray Radiation Protection

    RFI/EM Shielding

    Modular RFI/EM Shielded Rooms

    Lightning Protection

    Cathodic Protection

    Pre-Engineered Buildings

    Solarium

    Grandstands and Bleachers

    Tensioned Fabric Structures

    Swimming Pool

    Hot Tubs

    Water Storage Tanks

    Removal and Disposal of U.S. Federal Toxic Substances

    Solar Flat Plate Collectors

    Video Surveillance

    Intrusion Detection System

    Security Access System

    Electric Controls and Relays

    Clock and Program Systems

    Programmable Controllers

    Fire Alarm System

    Fire Alarm System Equipment

    Fire Protection Basic Materials and Methods

    Common Motor Requirements for Fire Suppression Equipment

    Vibration and Seismic Controls for Fire Suppression Piping and Equipment

    Identification for Fire Suppression Piping and Equipment

    Fire Suppression Piping Insulation

    Fire Pumps

    Fire Suppression Sprinklers

    Total Flooding Extinguishing System

    Standpipes and Fire Hoses

    Retrofit-Sprinkler Piping Cover System

     


    Division 14 – Conveying Systems

    Dumbwaiters

    Manual Dumbwaiters

    Passenger Elevators

    Freight Elevators

    Residential Elevators

    Custom Elevator Cabs and Hoistway Doors

    Elevator Equipment

    Passenger Elevator Control Systems

    Escalators

    Chutes

     


    Division 15 – Mechanical

    Non-Penetrating Rooftop Hangers and Supports

    Non-Penetrating Portable Rooftop Supports and Walkways

    Motors for Mechanical Equipment

    Common Motor Requirements for HVAC Equipment

    Vibration Isolation

    Vibration and Seismic Controls for HVAC Piping and Equipment

    Mechanical Identification

    Identification for HVAC Piping and Equipment

    Piping and Valve Identification

    Piping Insulation

    HVAC Piping Insulation

    Piping Safety Covers

    Equipment Insulation

    HVAC Equipment Insulation

    Duct Insulation

    Thermostatic Water Mixing Valves

    Piping Expansion Compensation

    Expansion Fittings and Loops for HVAC Piping

    Gages and Meters

    Meters and Gages for HVAC Piping

    Vertical In-Line Pumps

    Plumbing Piping

    Plumbing Specialties

    Hydronic Piping

    Hydronic Specialties

    Steam and Steam Condensate Piping

    Steam and Steam Condensate Specialties

    Refrigerant Piping and Specialties

    HVAC Pumps

    Chemical Water Treatment

    Fuel Oil Piping System

    Compressed Air System

    Medical Gas Systems

    Plumbing Fixtures

    Prefabricated Tubs and Showers

    Hospital Plumbing Fixtures

    Restroom Plumbing Fixtures

    Restroom Toilets, Urinals, and Faucets

    Restroom Lavatories

    Plumbing Equipment

    Swimming Pool Equipment

    Cast-Iron Boilers

    Finned Water-Tube Boilers

    Steel Water-Tube Boilers

    Fire-Tube Boilers

    Electric Boilers

    Forced Air Furnaces

    Direct Fired Air Units

    Fuel Fired Unit Heaters

    Breechings, Chimneys, and Stacks

    Refrigeration Compressors

    Packaged Water Chillers

    Air Cooled Water Chillers

    Centrifugal Water Chillers

    Water/Steam Absorption Water Chillers

    Gas Fired Absorption Water Chillers

    Gas Fired Unitary Absorption Water Chillers

    Induced Draft Cooling Towers

    Forced Draft Cooling Towers

    Ejector Cooling Towers

    Liquid Coolers

    Air Cooled Condensing Units

    Air Cooled Refrigerant Condensers

    Mini-Duct HVAC System

    Heat Exchangers

    Air Handling Units

    Small Split-System Heating and Cooling

    Packaged Roof Top Air Conditioning Units

    Packaged Terminal Air Conditioning Units

    Unitary Air Conditioners

    Computer Room Air Conditioning Units

    Computer Room Ac Units – Unitary Ceiling

    Water-to-Water Heat Pumps

    Evaporative Humidifiers

    Evaporative Pan Humidifiers

    Steam Humidifiers

    Sprayed Coil Dehumidifiers

    Terminal Heat Transfer Units

    Air Coils

    Floor-Heating and Snow-Melting Equipment

    Radiant-Heating Electric Cables

    Ducts

    Duct Accessories

    Sound Attenuators

    Air Curtains

    Centrifugal Fans

    Axial Fans

    Power Ventilators

    Carbon Monoxide Exhaust Systems

    Vehicle Exhaust System

    Air Terminal Units

    Air Outlets and Inlets

    Air Cleaning Devices

    Dust Collection Systems

    Thermostats

    Analog Control Equipment

    Digital Control Equipment

    Instruments and Control Elements

    HVAC Sequence of Operation

    Testing, Adjusting, and Balancing

     


    Division 16 – Electrical 

    Overcurrent Protective Device Coordination Study

    Grounding and Bonding

    Hangers and Supports

    Electrical Identification

    Minor Electrical Demolition

    Medium-Voltage Cable

    Building Wire and Cable

    Undercarpet Cable

    Manufactured Wiring Assemblies

    Conduit

    Surface Raceways

    Surface Nonmetallic Raceways

    Surface Metallic Raceways

    Surface Nonmetallic Raceways

    Underfloor Ducts

    Cable Trays

    Utility Columns

    Boxes

    Cabinets and Enclosures

    Wiring Devices

    Equipment Wiring

    Electrical Utility Services

    Electrical Sensing and Measurement

    Packaged Engine Generators

    Rotary Uninterruptible Power Supply

    Emergency Power Supply

    Converters

    Static Uninterruptible Power Supply

    Pad-Mounted Distribution Transformers

    Dry Type Transformers

    Power Factor Capacitors

    Overhead Line Materials

    Switchgear

    Air Interrupter Switches

    Medium-Voltage Oil Switches

    Medium-Voltage Motor Controllers

    Unit Substations

    Enclosed Circuit Breakers

    Enclosed Switches

    Enclosed Transfer Switches

    Remote Control Switching Devices

    Peak Load Controllers

    Enclosed Motor Controllers

    Motor Control Centers

    Variable Frequency Controllers

    Enclosed Contactors

    Switchboards

    Panelboards

    Feeder and Plug-In Busway

    Power Distribution Units

    Fuses

    Interior Luminaires

    Exterior Luminaires

    Obstruction and Landing Lights

    Theatrical Lighting

    Structured Telecommunications Cabling and Enclosures

    Nurse Call System

    Intercom System

    Television Distribution System

    Public Address and Music Equipment

     


     

    Download the excel file which including the full coding system: wbs and division of work excel spread sheet

     


     

    1 2 3

    Tag:coding system, construction WBS, planning wbs, WBS, work breakdown structure

    • Share:
    Hany Ismail, MSC, PMP
    Hany Ismail, MSC, PMP

    Hany Ismael is the founder and CEO of Planning Engineer Est. in Egypt. He has started his career back in 2003 as a site engineer, technical office engineer, planning engineer, planning manager, and finally planning department manager where he has been involved in several mega construction projects in Egypt and Saudi Arabia. In 2016, he established his own company in Egypt “Planning Engineer Est.” Hany gained his MSc degree in project management from Liverpool University-UK 2013-2016, PMP certified from PMI-USA 2010, and BSc Civil Engineer Tanta University-Egypt 2003. Hany provided more than 3,500 hours of planning and project management training on his website planningengineer.net, YouTube channel, and offline courses since 2011. He enjoys teaching project management in simple and practical way, and he developed several planning tools, techniques and courses.

    Previous post

    Top 10 Primavera Interview questions and Model Answers
    February 14, 2013

    Next post

    Earth moving Equipment function and standard Productivity
    February 16, 2013

    You may also like

    20220629_013616
    Primavera P6 Excel Import/Export Require Microsoft Access [Solved]
    29 June, 2022
    Remove Actuals using Global Change cover
    Remove Primavera P6 Actuals using Global Change
    24 January, 2022
    Bulk Delete Relationships in P6 cover
    Bulk Delete Relationships in P6
    20 January, 2022

      3 Comments

    1. blank
      Hasan Jlelaty
      February 15, 2013
      Log in to Reply

      this is very important subject.

    2. blank
      Issa Abbz
      March 20, 2013
      Log in to Reply

      very informative and important /…

    3. blank
      Azad Pasha
      October 10, 2013
      Log in to Reply

      Hva you heared of OmniClass construction classification system? I will send a file concerning that

    Leave A Reply Cancel reply

    You must be logged in to post a comment.

    Cart

    0

    Planning Courses

    Cost Control for Construction Projects

    Cost Control for Construction Projects

    $299.00
    Power Bi Monitoring and Controlling with P6

    Power Bi Monitoring and Controlling with P6

    $299.00
    Advanced Planning 3 Courses Package

    Advanced Planning 3 Courses Package

    $499.00
    Data Management and Reporting

    Data Management and Reporting

    $199.00
    Primavera Online Basic Course -Arabic

    Primavera Online Basic Course -Arabic

    $99.00
    Professional Planning Engineer (PPE)

    Professional Planning Engineer (PPE)

    $335.00
    Claims Management and (EOT)

    Claims Management and (EOT)

    $175.00
    Primavera Online Basic Course -English

    Primavera Online Basic Course -English

    $99.00

    Follow Us:

    About Us | Contact Us | Terms of Service | Privacy Policy | Refund Policy

    Copyright ©2012- 2018 planningengineer.net | All materials, unless otherwise noted, were developed originally for Planning Engineer Website. In the event that there is still a problem or error with copyrighted material, the break of the copyright is unintentional and noncommercial and the material will be removed immediately upon presented proof.

    • Planning Courses
    • Planning Jobs
    • Planning Blog
    Posting....