Hany Ismail, MSC, PMP
KeymasterHello Engineer Salman, nice to see you here.
April 13, 2022 at 9:09 am in reply to: Lesson 2.3 – Prepare B.O.Q ( Add Ref. No & Merge Items description ) #110867Hany Ismail, MSC, PMP
KeymasterHello Engineer Muhammad,
The best way to find out the problem is to execute the Macro step by step using F8.
If you cannot solve this issue, please email me your file at [email protected]ngineer.net and I will check it out.
Hany Ismail, MSC, PMP
KeymasterHello Engineer Khurram Shahzad, Nice to see you here.
Hany Ismail, MSC, PMP
KeymasterHello Engineer Hammad. Nice to see you here.
Hany Ismail, MSC, PMP
KeymasterHello Sandeep, nice to meet you here.
Hany Ismail, MSC, PMP
KeymasterHello Sylvere Ndayizeye. Nice to see you here.
Hany Ismail, MSC, PMP
KeymasterHello Engineer Nabil, Nice to see you here
Hany Ismail, MSC, PMP
KeymasterHello Engineer,
If you can elaborate and include some screenshots of what you are trying to do i might help 🙂
February 3, 2022 at 10:16 am in reply to: Productivity rate for oil & gas field construction work #109618Hany Ismail, MSC, PMP
KeymasterDear Engineer Faisal,
Unfortunately, I don’t have something specific for Oil and Gas. However, the Productivity rates software might help: https://planningengineer.net/product/productivity-rates-pc-software/Hany Ismail, MSC, PMP
KeymasterThat is great 🙂
Hany Ismail, MSC, PMP
KeymasterDear Engineer,
What I prefer to do in windows analysis is to have one event per window. It gives a more realistic analysis.
And since the client asked for it, just do it one by one. Remember the claims need to be dealt with some diplomatic negotiations to get what you need.Hany Ismail, MSC, PMP
KeymasterHello Engineer Razme. Nice to see you here.
Hany Ismail, MSC, PMP
KeymasterHello Engineer Syed. Nice to see you here.
Hany Ismail, MSC, PMP
KeymasterDear Engineer,
I have created the following article about the calendar tips and tricks, it will be useful for you:
Hany Ismail, MSC, PMP
KeymasterHello Jaymincs, Check out this post: https://planningengineer.net/calculate-duration-in-p6-based-on-scope/
-