March 25, 2017 at 12:22 pm
#25269

Participant
Dear Nickijg ,
In our sheet we put the crew productivity as Hrs/unit , which means how many hours should be taken to get 1 unit form this item.
Attached photo Exmaple :
that means : We need 2 HRs to get 1m3 form the plain concrete with its relevant professions.