A. i have some of the projects in my company which does’t have BOQ because the we are Client and Contractor at the same time for these projects, so what i can consider for such kind of projects?
B. Sometimes they say cash flow should be more in early months(front loaded) , logically its not. but they want because of above scenario. so should i consider it during cost loading, ex. in my first 3 months, total activities which are completed and in progress have 3million cost but they want to show 6million so i can consider their choice or according to BOQ?
please advice.