Dear Faraz , Yes there is no any quantity for the shuttering and the steel re baring , actually you don’t need their quantity and it is not the planning engineer to make quantity surveying you can only collect the quarantines it is for the BOQ and check the main activities to create work packages and activity list and so on
Yes sir but if we are planning for example a slab we need to know how many steel fixer are required for completing that work.
like the attachment i have below.