1- I add New material resource
2- only change price/unit from 0 to 1.
3- then add one activity assign resource
4-export spreadsheet for resource assignment
5- add activity id and activity amount sum in ” Budgted units”
6- Import that same file and result every activity coming 8 times more amount,