the old problem got fixed when i deleted any extra sheets in importing file. but now i have a new error when trying to fix the wrong activities which were outside the wbs. it says the “Process did not complete successfully. See log file for details.”
Excel Import log started : 02-Jun-20
INFO: Importing Global Data…
INFO: Importing Project Data…
INFO: Importing:
WARNING: TASK: Failed to resolve foreign key for field WBS Code with value NEWPROJ-2.test.St-L.St-H. Field cleared.
WARNING: TASK: Failed to resolve foreign key for field WBS Code with value NEWPROJ-2.test.St-I.swws. Field cleared.
WARNING: TASK: Failed to resolve foreign key for field WBS Code with value NEWPROJ-2.test.St-I.swws. Field cleared.
WARNING: TASK: Failed to resolve foreign key for field WBS Code with value NEWPROJ-2.test.St-I.swws. Field cleared.
WARNING: TASK: Failed to resolve foreign key for field WBS Code with value NEWPROJ-2.test.St-I.swws. Field cleared.
these are just few lines whereas its a big log file.
what could be the reason for this and how to solve these activities.
Note: the previous activities were imported all successfully except for these ones