Dear Jawad,
Kindly consider the below points.
1. The response time taken by consultant is beyond 7 days as planned.
2. Instruction to hold the fixation of TV & PA can be a delay event since it will affect the authority inspection and getting the NOC from authorities.
3. Delay in payment can affect the release of payment to suppliers and sub contractors. The project start date was 10th March 2012 and the first payment was not released even on 15th October 2012.
4. No works after 6 pm may affect. The concrete pouring is done at night in some project. This may affect the car park and septic tank concreting. May not be a critical delay.
Thanks,