in the event no 4 LIGHTING FIXTURES& SWITCHES Procurement, i notified that this activity is critical on the baseline, also this activity is not on the longest path
when we applied even this activity did not case dealy for the project, could you tell me something about critical path and longest path help me to forecast if this activity may oy may not delay the project?
I think if the activity on both critical path and longest path that means this activity will delay the whole project if it dealy
is that right?