Dear Engineer Muhammed,
The event should consider the time and effect. We are not talking here about cost impact, we talk about time impact. So, if i gave you an instruction at early stage of the project to modify something at the end of the project, would you consider this an event? You have plenty of time to do it without any impact to the project completion date.
Best Regards,
Hany