April 8, 2019 at 3:32 am
#55064

Keymaster
Yes, you should know the start date of the project from the contract documents. However, sometimes it is mentioned the start date is after the letter of award, after the authorities approval of a certain document, after subcontractor xx completion of his works. You need then to find out the correct start date and fix it in your baseline schedule to be a contractual document.