July 6, 2018 at 6:11 pm
#33699

Keymaster
simply do not use baseline with actuals. I believe you just modified your progress schedule and kept the actual information. I would recommend to start with your baseline and change the original durations and the links to match what happens in actual so you will have a baseline without actual that will give you accurate planned/earned values.