June 19, 2017 at 10:53 am
#27460

Participant
Dear Ismail ,
Orcale primavera define the Data Date time as the first moment new work can start in the schedule , so it automatically put the first time of your calendar.
I think you want to run the schedule at the end of the day , but you can do it by schedule by the next day date and this will reflect the actual of your progress.
Best Regards,
Mahmoud Omara