There are two ways to Find out the Delayed Activities that delay the Milestone.
A. The first Way is to Filter the delayed Milestone as the Following
North Road Finish is a Milestone and has a “Must Finish by a date” which makes it have a high Negative Total Float.
So, to get the Activities that cause the delay of the milestone:
The first filter is by using the milestone’s Activity ID and then applying it.
This will give you the Milestone only.
Then go to “Relationships”, view them all, and click “Go To” on the driving activities to the Milestone.
After you “Go To” to the Driving Activities, the Driving Activities will appear with the same total float.
B. The Second Way is to make the Milestone Must Finish by Earlier date to increase the Total Float
Project Finish Milestone has a -30 days total float so it may have many activities with the same total float.
So you need to increase the total float to ensure that the related activities only have the same float. We will make the total float equal to -50 days and it has a Constraints Finish on an earlier date, so it is easier to filter the activities with the same total float to recognize them.
The Filter will be “Total float” is “Less than -49” to get you the activities with a total float of -50.
It will show the driving delayed activities of the Milestone.
These activities are the activities that delayed the Milestone.