    • EOT Claims – Save your company Rights

    EOT Claims – Save your company Rights

    • Posted by Mahmoud El Refaie
    • Categories Project Management
    • Date June 15, 2017
    • Comments 1 comment

    EOT Claims – Save your company Rights

     Be your Company Guard

     

    The construction industry is complicated by natural, involves too many parties (Client, Consultant, Main contractors, Sub contractors, and Suppliers), also having a lot of constraints you have to take in your consideration and deal with ( Time – Budget- scope –Risk- Resources – Quality – Customer satisfaction)

    Therefore, each one of the involved parties does not want to lose any additional money or time rather than the project original budget. Accordingly, when something goes wrong during the project life cycle, one or more parties of the project will raise dispute to prove which fault is it. Yes. It is as simple as this. However, the real battle starts when the dispute begins. The winner who could prove that the mistake was not his/her fault and s/he was a victim of this mistake and he deserve compensation (Time, Money, or Both).

    Because of the delays  whatever the reason of it, any delay produces an “Entitlement”, your role is to protect and defend your rights. This applies in both cases (contractor side or the client side).

    In this article, we will try to give you some important information about Claims in general and EOT Claims as the most type of claims in construction industry, that will help you to play the role of the company Guard, defend/get Entitlement for your company.

    What is Claim?

    Claim doesn’t mean problem, simply in planning engineer Est. (Our Company) we define Claim as an application or request for any entitlements or rights reference to the contract.

    Why Claims in Construction industry?

    Claims is the contractual method that you can get or defend on your rights with specific procedures and steps, it simply organize the way for request and approve any entitlement between the contractor and the client.

     

    blank

    According to the previous definition and reference to your role and position in the construction project, you may be one of the following:

    • Contractor Planner: You have to prepare the claims and request any entitlement, you may have as per the contract with the employer and make analysis for any delays, check the delays impact on the time schedule , convert it into number of days and also prolongation cost if any.
    • Client Planner “Representer” : You have to review any claim requested by the contractors and check the reason of the delays and also check any delays impact on the project time schedule.
    • Consultant Planner :

    As consultant you have to play as fair party to review any claims from the contractors and review the delays impact, give final decision for any claim.

    What are Types of Claims?

    As illustrated in the chart below, following are some types of claims, the most important and common types are:

     

    blank

               

    Why EOT Claims?

    EOT Claims are the most complicated claims and they are subject to huge argument between the claim parties. Furthermore, although the extension of time claim would increase the project duration by a certain number of days, but once it is approved, another claim of cost will be raised based on the EOT to recover the delays (or prolongation) costs incurred due to the delays.

    Planning Engineer Est. has a golden rule for any EOT Claim, and we apply this rule in all our claims preparation. Time = Money

     

    blank

     

     Making EOT Claims Responsibility?

    In planning Engineer Est. , we believe that the Planning Engineer is the most organized person in the construction team. Also, Planning Engineers have the project history and of course they have the access to the project time schedule which is the base of the EOT claim. Accordingly, Planning Engineer should collect all relevant data from the project team and be responsible for the final product (the EOT).

    Planning Engineer is responsible for making EOT Claims as s/he has good understanding and access of the following:

    1- Project Contract Special Conditions

    2- Project Contract General Conditions

    3- Project Time Baseline

    4- Project updates and progress

    5- Project documents” BOQ – Drawings – Specifications”.

    6-Communication channels

    blank

    If you are interested to get more practical and valuable knowledge and procedure of making successful EOT Claim, you can check our EOT Claims Workshop from the following Link: https://planningengineer.net/courses/claims-management-and-delays-analysis-online-workshop/

    ——————————————-

    We hope you enjoy our journey today

    Hope to receive your feedback and recommendations

    Thank You…:):)

    Tag:Claims Analysis, Construction Claims, EOT, EOT Claims

    • Share:
    author avatar
    Mahmoud El Refaie

    Mahmoud El Refaie Omara ,Civil Engineering Informatics Specialist - Planner Engineer ,worked as site and technical office engineer for 4 years ,In planning Engineering my role is filling the gap between the Planning Engineering and Engineering Informatics by developing smart Engineering Informatics solutions, which quick your work and make your tasks more easy without any repetitive or hard work.

    Previous post

    10 Successful Tips to Fail in Planning of Construction Projects
    June 15, 2017

    Next post

    4 Successful Steps for Getting your EOT Claim
    June 18, 2017

    You may also like

    img_0142.jpg
    How to perform Cost Control in Construction Projects
    29 September, 2020
    getty_506903004_200013332000928076_348061
    How to change Your Career to a Planning Engineer
    10 December, 2019
    Claim Specialist
    Difference between Claim Specialist and Delay Analyst
    3 March, 2019

      1 Comment

    1. blank
      alyflowery
      June 15, 2017
      Log in to Reply

      great article

    Leave A Reply Cancel reply

    You must be logged in to post a comment.

    Cart

    0

    Planning Courses

    Cost Control for Construction Projects

    Cost Control for Construction Projects

    $299.00
    Power Bi Monitoring and Controlling with P6

    Power Bi Monitoring and Controlling with P6

    $299.00
    Advanced Planning 3 Courses Package

    Advanced Planning 3 Courses Package

    $499.00
    Data Management and Reporting

    Data Management and Reporting

    $199.00
    Primavera Online Basic Course -Arabic

    Primavera Online Basic Course -Arabic

    $99.00
    Professional Planning Engineer (PPE)

    Professional Planning Engineer (PPE)

    $335.00
    Claims Management and (EOT)

    Claims Management and (EOT)

    $175.00
    Primavera Online Basic Course -English

    Primavera Online Basic Course -English

    $99.00

    Follow Us:

    About Us | Contact Us | Terms of Service | Privacy Policy | Refund Policy

    Copyright ©2012- 2018 planningengineer.net | All materials, unless otherwise noted, were developed originally for Planning Engineer Website. In the event that there is still a problem or error with copyrighted material, the break of the copyright is unintentional and noncommercial and the material will be removed immediately upon presented proof.

    • Planning Courses
    • Planning Jobs
    • Planning Blog
    Posting....