      Construction Projects Planning Q&A 23-Jan-2022

      • Date January 23, 2022
      • Tags concurrent delay, free training, Level of effort and WBS summary, longest path and the critical path, planning career, Primavera P6 Course, PV=EV, reduce total float, Retained logic ve Progress override

      Live Construction Planning Discussion where we discussed the following topics:

      Mechanical Engineering Background I had completed the Primavera P6 Course in India. but till now am not getting Job as a Planning engineer please suggest
      Very common issue. Making PV=EV while creating a revised schedule. (Without splitting activities). What is the way?
      kindly explain the difference between the longest path and the critical path? plz. I am confused
      Do you have a free training session but less fee on the certificate?
      what is the concurrent delay?
      How to reduce total float in a schedule?
      Master’s Degree useful or not
      we need ur opinion about BIM please can u advise us, thnx a lot sir
      Can you explain for us deferences between progress tracking based on unit one time or cost loaded one time?
      how to become advanced in excel?
      Sir how to track a project with actual quantity in ms project?
      If there is multiple longest path what is the method for showing each path separately?
      how can I register for your paid course, any details pls?
      PMI -SP OR AACE PSP?
      Hi. when there is concurrent delay what we should do? can we say that we should calculate them as client delays?
      What is the difference between a recovery schedule and a revised schedule?
      I am a quantity surveyor by profession but I want really to be a planning engineer and what can you advise to me. I already started learning Primavera P6. How can I enter into a planning career?
      Sir, How to get wbs activities extracted for multiple packages. Like there are 10 packages and if I want to get only engineering wbs and its activities how to get the same in primavera?
      what good steps to preparing a revised program schedule
      what are the new software and tools planners need to learn for the next decade?
      I am QC in civil engineering roads and buildings for 4 years. I am planning to move into a planning Career. what is ur advice?
      what’s the best way to represent the relationship between concrete formwork and fixing steel, considering fixing steel may start 2day after the start of formwork, and form work should end after the end of fixing steel.
      what’s the best way to get an actual link with the plan !? by mean I wanna know how can I get the best KPI from my team !?
      If I register for your courses, can I enter the course contents for a limited time or lifelong?
      front loading and backloading
      What is the difference between retained logic & override logic?
      dear, can you please tell me how can I load resources from my BOQ to primavera?
      Sir, please tell me how can I check all links that I have done in planned are right?
      can I make the same cost loading in your video of cost loading? can I load all resources using vlookup?
      What is the use of the Level of effort and WBS summary activity type?
      What is the use of % complete type? There are three methods? 1. Duration 2. Physical 3. Units
      What are the better options as per your experience for scheduling the progressed activities? In Retained logic ve Progress override?
      if the free float consumed of activities would that activities be critical??
      How to check the schedule after preparation?
      Hi Eng.Hany, What Do You Prefer Duration Percentage Complete or Physical?


      Keep in Touch

      Twitter: https://twitter.com/PlanningEEst
      YouTube: https://www.youtube.com/c/PlanningengineerNet/
      Linked in: https://www.linkedin.com/company/planning-engineer-est/
      Instagram: https://www.instagram.com/planningengineerest/
      FaceBook: https://www.facebook.com/PlanningEngineerDotNet
      WhatsApp: +201277767728
      Email: [email protected]


      Watch the Recorded Version of this Stream:

      Tag:concurrent delay, free training, Level of effort and WBS summary, longest path and the critical path, planning career, Primavera P6 Course, PV=EV, reduce total float, Retained logic ve Progress override

      • Share:
      author avatar
      Hany Ismail, MSC, PMP

      Hany Ismael is the founder and CEO of Planning Engineer Est. in Egypt. He has started his career back in 2003 as a site engineer, technical office engineer, planning engineer, planning manager, and finally planning department manager where he has been involved in several mega construction projects in Egypt and Saudi Arabia. In 2016, he established his own company in Egypt “Planning Engineer Est.” Hany gained his MSc degree in project management from Liverpool University-UK 2013-2016, PMP certified from PMI-USA 2010, and BSc Civil Engineer Tanta University-Egypt 2003. Hany provided more than 3,500 hours of planning and project management training on his website planningengineer.net, YouTube channel, and offline courses since 2011. He enjoys teaching project management in simple and practical way, and he developed several planning tools, techniques and courses.

      Previous post

      Bulk Delete Relationships in P6
      January 23, 2022

      Next post

      Remove Primavera P6 Actuals using Global Change
      January 24, 2022

      You may also like

      How to become a planning engineer
      How to be prepared to work as a junior planning engineer?
      22 May, 2022
      Hany Live 15-Mar-2022
      Construction Projects Planning Q&A 15-March-2022
      15 March, 2022
      Live Streaming
      Construction Projects Planning Q&A 08-Jan-2022
      8 January, 2022

      Leave A Reply Cancel reply

      You must be logged in to post a comment.

      Cart

      0

      Planning Courses

      Cost Control for Construction Projects

      Cost Control for Construction Projects

      $299
      Power Bi Monitoring and Controlling with P6

      Power Bi Monitoring and Controlling with P6

      $299
      Advanced Planning 3 Courses Package

      Advanced Planning 3 Courses Package

      $499
      Data Management and Reporting

      Data Management and Reporting

      $199
      Primavera Online Basic Course -Arabic

      Primavera Online Basic Course -Arabic

      $99
      Professional Planning Engineer (PPE)

      Professional Planning Engineer (PPE)

      $335
      Claims Management and (EOT)

      Claims Management and (EOT)

      $175
      Primavera Online Basic Course -English

      Primavera Online Basic Course -English

      $99

      Follow Us:

      About Us | Contact Us | Terms of Service | Privacy Policy | Refund Policy

      Copyright ©2012- 2022 planningengineer.net | All materials, unless otherwise noted, were developed originally for Planning Engineer Website. In the event that there is still a problem or error with copyrighted material, the break of the copyright is unintentional and noncommercial and the material will be removed immediately upon presented proof.

      • Planning Courses
      • Planning Jobs
      • Planning Blog

      Login with your site account

      Lost your password?

      Not a member yet? Register now

      Register a new account

      Are you a member? Login now

      Posting....